Line 55: | Line 55: | ||
'''Notification date''' | '''Notification date''' | ||
- | :* Mapping [[ | + | :* Mapping [[CT_bo#Notification_Date]] |
+ | :* Logic: This date MUST be set before any other dates | ||
'''Authorized on''' | '''Authorized on''' | ||
+ | :* Mapping [[CT_bo#Authorized_On]] | ||
+ | :* Logic: This date CANNOT be set until the previous date has been set | ||
'''Actual collection''' | '''Actual collection''' | ||
+ | :* Mapping [[Container#Actual_Export_Pick_Up_Date]] | ||
+ | :* Logic: This date CANNOT be set until the previous two dates have been set | ||
'''Actual delivery''' | '''Actual delivery''' | ||
+ | :* Mapping [[Container#Actual_Delivery_Date]] | ||
+ | :* Logic: This date CANNOT be set until the previous three dates have been set | ||
'''Origin terminal ATD''' | '''Origin terminal ATD''' | ||
+ | :* Mapping [[CT#Origin_Terminal_Actual_Date]] | ||
+ | :* Logic: This date CANNOT be set until the previous four dates have been set | ||
'''Port of loading ATD''' | '''Port of loading ATD''' | ||
+ | :* Mapping [[CT#Port_Of_Loading_Actual_Date]] | ||
+ | :* Logic: This date CANNOT be set until the previous five dates have been set | ||
'''Port of tranship (if applicable) ATA''' | '''Port of tranship (if applicable) ATA''' | ||
+ | :* Mapping [[CT#Trans_Shipment_Actual_Date]] | ||
+ | :* Logic: This date CANNOT be set until the previous six dates have been set | ||
'''Port of discharge ATA''' | '''Port of discharge ATA''' | ||
+ | :* Mapping [[CT#Port_Of_Discharge_Actual_Date]] | ||
+ | :* Logic: This date CANNOT be set until the previous seven dates have been set | ||
'''Destination terminal ATA''' | '''Destination terminal ATA''' | ||
- | + | :* Mapping [[CT#Destination_Terminal_Actual_Date]] | |
- | + | :* Logic: This date CANNOT be set until all of the previous dates have been set | |
=== MOT:Air === | === MOT:Air === |
Revision as of 20:37, 2 November 2010
Contents |
General Info
Dates on CT2 are supposed to be confirmed in the specific orders.
Business Requirements
- Operator should not be allowed to enter dates in incorrect orders. If a date is entered out of the order, system should show an error message and the date should not be saved.
- These dates are under different tabs per mode of transportation.
Detail Requirements
- NOTE: Each date below MUST be entered in order as the following order dates below.
- Example: MOT: Ocean LCL, Destination Terminal ATA date cannot be entered before Port of discharge ATA date is entered. And Port of discharge ATA cannot be entered before Port of Tranship ATA date is entered (if this date is application),...etc
MOT:Ocean LCL
Notification Date
- Mapping: CT_bo#Notification_Date
- Logic: This date MUST be set before any other dates
Authorized on
- Mapping CT_bo#Authorized_On
- Logic: This date CANNOT be set until the previous date has been set
Export pick up actual date
- Mapping CT_bo#Estimated_Export_Pick_Up_Date
- Logic: This date CANNOT be set until the previous two dates have been set
Origin Terminal actual ATD
- Mapping CT_bo#Origin_Terminal_Actual_Date
- Logic: This date CANNOT be set until the previous three dates have been set
Port of loading actual ATD
- Mapping CT_bo#Port_Of_Loading_Actual_Date
- Logic: This date CANNOT be set until the previous four dates have been set
Port of Tranship ATA (if applicable)
- Mapping CT_bo#Trans_Shipment_Actual_Date
- Logic: This date CANNOT be set until the previous five dates have been set
Port of discharge ATA
- Mapping CT_bo#Port_Of_Discharge_Actual_Date
- Logic: This date CANNOT be set until the previous six dates have been set
Destination Terminal ATA
- Mapping CT_bo#Destination_Terminal_Actual_Date
- Logic: This date CANNOT be set until the previous seven dates have been set
Delivery date
- Mapping CT_bo#Actual_Delivery_Date
- Logic: This date CANNOT be set until all of the previous dates have been set
MOT:Ocean FCL
Notification date
- Mapping CT_bo#Notification_Date
- Logic: This date MUST be set before any other dates
Authorized on
- Mapping CT_bo#Authorized_On
- Logic: This date CANNOT be set until the previous date has been set
Actual collection
- Mapping Container#Actual_Export_Pick_Up_Date
- Logic: This date CANNOT be set until the previous two dates have been set
Actual delivery
- Mapping Container#Actual_Delivery_Date
- Logic: This date CANNOT be set until the previous three dates have been set
Origin terminal ATD
- Mapping CT#Origin_Terminal_Actual_Date
- Logic: This date CANNOT be set until the previous four dates have been set
Port of loading ATD
- Mapping CT#Port_Of_Loading_Actual_Date
- Logic: This date CANNOT be set until the previous five dates have been set
Port of tranship (if applicable) ATA
- Mapping CT#Trans_Shipment_Actual_Date
- Logic: This date CANNOT be set until the previous six dates have been set
Port of discharge ATA
- Mapping CT#Port_Of_Discharge_Actual_Date
- Logic: This date CANNOT be set until the previous seven dates have been set
Destination terminal ATA
- Mapping CT#Destination_Terminal_Actual_Date
- Logic: This date CANNOT be set until all of the previous dates have been set