2011 Aug Sept

From UG

Jump to: navigation, search


Contents

Intro

Staging 19-Sep-11 Production 22-Sep-11

Number of Days 19 --> Holiday Aug24 Ukrain independent day

Plan to the Board

See it by selecting "All projects" and S#="8d"

Kostya

File:KostyaAug.JPG

Please note that mantis 3117, Simon proposes a new requirement, please discuss with Alex. However the bug still need to fix. Up to you whether the new requirement can be done at the same time as the fixing bug or you would like to fix the bug first and work on the new requirement in the future. If the bug can be fixed with the new requirement, this task is not necessary to be included in this sprint.

Sasha

File:SashaAug.JPG

Misha

File:MishaAug.JPG

Andriy

File:AndriyAug.JPG

Andrei

File:AndreiAug.JPG

Roma

File:RomaAug.JPG

Personal tools