ASN 20 Timeline

From UG

Revision as of 17:13, 12 September 2012 by Alex (Talk | contribs)
Jump to: navigation, search


Contents

2012

July

  • July 1:
    • project STARTED
      • (scope/approach was reduced from ASN/I-Portal to fast track strictly ASN 2.0)
      • Alex took over this project from Tira
  • July 1 - July 13 (2 weeks):
    • Requirements Phase - completed
  • July 16 - 20 (1 week):
    • Elco visit + Alex's PTO
  • July 23 - Aug 3 (2 weeks):
    • Solution (Architecture/Design) Phase - completed

August

Week of Aug 6 to 12

  • Mon, 6: Review of Solution (Marc/Alex), collecting feedback (significant changes requested)


Week of Aug 13 to 19

Week of Aug 20 to 26

Week of Aug 27 to Sep 2

Sept

Mon 10 to Sun 16

  • Mon
    • Final spec sign off meeting with Simon/Marc
    • Agreement with Kostya on Architecture / resource allocation / schedule
    • Agreement with Perry on resource allocation / schedule
  • Tue
    • most mantis tasks created and assigned
    • schedule for next week finalized / disseminated
  • Wed
  • Th
    • all tasks estimated
  • Fri
    • proj plan is in place
    • proj kick off meeting

By the end of this week:

  • AK: SOW 2,3,4,5? completed;
  • Kostya: TBD
  • Sasha: TBD
  • Misha: TBD

Mon 17 to Sun 23

  • Mon
  • Tue
  • Wed
  • Th
  • Fri

By the end of this week:

Mon 24 to Sun 30

  • Mon
  • Tue
  • Wed
  • Th
  • Fri

By the end of this week:

October

Mon 1 to Sun 7

  • Mon
  • Tue
  • Wed
  • Th
  • Fri
  • By the end of this week:

Mon 8 to Sun 14

  • Mon
  • Tue 16
  • Wed
  • Th 11
    • ASN 20 demo to Marc/Simon
  • Fri
  • By the end of this week:

Mon 15 to Sun 21

  • Mon
  • Tue 16
    • ASN 20 demo to EA
  • Wed
  • Th
  • Fri
  • By the end of this week:

L0 Schedule per Perry (outdated)

Option 1 (crash - with new developers added and more aggressive schedules)

Construction	8/20/12	- 9/7/12   days=15  Sasha, AK
Verif-n (UAT)	9/10/12	- 9/21/12  days=10  Sasha, Roma, AG, New Dev 2 (as QA)
Buffer         9/24/12	- 10/5/12  days=10  Sasha, Roma, AG


Option 2 (baseline)

Construction	8/20/12	- 9/7/12	days=15  Sasha, AK
Verification	9/10/12	- 9/28/12	days=15  Sasha, Roma, AG
Buffer         10/1/12	- 10/19/12	days=15  Sasha, Roma, AG