ASN 20 Timeline
From UG
Contents |
2012
July
- July 1:
- project STARTED
- (scope/approach was reduced from ASN/I-Portal to fast track strictly ASN 2.0)
- Alex took over this project from Tira
- project STARTED
- July 1 - July 13 (2 weeks):
- Requirements Phase - completed
- July 16 - 20 (1 week):
- Elco visit + Alex's PTO
- July 23 - Aug 3 (2 weeks):
- Solution (Architecture/Design) Phase - completed
August
Week of Aug 6 to 10
- Mon, 6: Review of Solution (Marc/Alex), collecting feedback (significant changes requested)
- Mon-Fri: work on Final Version
Week of Aug 13 to 17
- Mon:
- Final version of Solution completed and disseminated
- Suggested WBS Work Breakdown Structure disseminated
- Tue:
- WBS approved
- Mantises created; developers assigned for estimation
- Fri:
- Tasks estimated
- Project Schedule / Release Date adjusted accordingly to estimates
Week of Aug 20 to 24
1st week of Construction/QA.
L0 Schedule per Perry
Construction 8/20/12 - 9/7/12 days=15 Verification 9/10/12 - 9/21/12 days=10 Buffer 9/24/12 - 10/5/12 days=10