UG:IP2 Timeline

From UG

Revision as of 21:02, 27 June 2012 by Alex (Talk | contribs)
Jump to: navigation, search


Contents

2012

July

  • 13 / Fri
    • Timeline will be converted from L0 (initial) to L1 (fine) estimates
  • 26 / Th
    • Shipper module: release to UAT

Aug

  • 23 / Th
    • Planner module: release to UAT

Sep

  • 27 / Th
    • Jaguar module: release to UAT

Oct

  • 25 / Th
    • Misc module: release to UAT

Nov

  • TBD
    • Release to prod

Dec

Personal tools