POEM Project Plans

From UG

Revision as of 15:36, 25 June 2012 by Perry (Talk | contribs)
(diff) ← Older revision | Current revision (diff) | Newer revision → (diff)
Jump to: navigation, search


% Complete Task Name Duration Start Finish
44%POEM Prototype139 daysMon 5/21/12Thu 7/12/12
0% Start POEM Prototype10 daysMon 5/21/12Mon 5/21/12
100% Infrastructure (Server Builds & Configuration)2 daysWed 5/23/12Thu 5/24/12
100% Build new DEV environment2 daysWed 5/23/12Thu 5/24/12
88% Requirements (BRD & SRS Document)17 daysMon 5/21/12Tue 6/12/12
100% Hold Requirements/Discovery Sessions15 daysMon 5/21/12Fri 6/8/12
75% Document Requirements into Wiki15 daysMon 5/21/12Fri 6/8/12
100% Create UML Diagrams for ALL use cases15 daysMon 5/21/12Fri 6/8/12
0% Identify use cases for System Generated Notifications2 daysMon 6/11/12Tue 6/12/12
43% Design Documentation20 daysMon 5/21/12Fri 6/15/12
77% Create Mock-Ups18 daysMon 5/21/12Wed 6/13/12
100% Create mock ups for PO List4 daysMon 5/28/12Thu 5/31/12
100% Create mock ups for PO Editor3 daysFri 6/1/12Tue 6/5/12
100% Create mock up for ASN-PO interface1 dayFri 6/8/12Fri 6/8/12
100% Create mock ups for SKU Editor2 daysMon 5/21/12Tue 5/22/12
0% Create mock ups for Reporting (Download to Excel ONLY)1 dayMon 6/11/12Mon 6/11/12
0% Create mock ups for Shipping Document Center2 daysTue 6/12/12Wed 6/13/12
0% Write SOW110 daysMon 6/4/12Fri 6/15/12
0% Complete POEM Prototype1 Documentation0 daysMon 6/4/12Mon 6/4/12
49% Construction21 daysMon 6/4/12Mon 7/2/12
0% Start POEM Prototype1 Construction0 daysMon 6/4/12Mon 6/4/12
75% New Purchase Order Objects8 daysMon 6/4/12Wed 6/13/12
75% Build PO Domain Objects8 daysMon 6/4/12Wed 6/13/12
75% Build DB tables8 daysMon 6/4/12Wed 6/13/12
75% Build Service Objects8 daysMon 6/4/12Wed 6/13/12
75% Build PO Functions8 daysMon 6/4/12Wed 6/13/12
50% Review/Update/Fulfill Purchase Orders14 daysMon 6/4/12Thu 6/21/12
75% Build PO List UI6 daysMon 6/4/12Mon 6/11/12
75% Build PO Editor UI6 daysTue 6/12/12Tue 6/19/12
0% Build use cases to review/update Purchase Orders3 daysThu 6/14/12Mon 6/18/12
0% Build use cases to Fulfill Purchase Orders3 daysTue 6/19/12Thu 6/21/12
0% Build use cases to send System Generated Notifications1 dayFri 6/29/12Fri 6/29/12
0% Shipping Documents13 daysThu 6/14/12Mon 7/2/12
0% Build Shipping Document Center UI3 daysTue 6/26/12Thu 6/28/12
0% Build Download/Upload function2 daysFri 6/29/12Mon 7/2/12
0% Build Shipping PDFs5 daysThu 6/14/12Wed 6/20/12
0% Build Shipping Labels1 dayThu 6/14/12Thu 6/14/12
0% Build Pro-Forma Regulatory Documents1 dayTue 6/19/12Tue 6/19/12
0% Build Packing Lists1 dayWed 6/20/12Wed 6/20/12
0% Reporting5 daysThu 6/21/12Wed 6/27/12
0% Build Download to Excel Feature5 daysThu 6/21/12Wed 6/27/12
0% SKU Management4 daysWed 6/20/12Mon 6/25/12
0% Build SKU Editor User Interface4 daysWed 6/20/12Mon 6/25/12
0% Validation17 daysWed 6/20/12Thu 7/12/12
0% Quality Assurance Tests17 daysWed 6/20/12Thu 7/12/12
0% Execute QA tests for Review/Update/Fulfill Purchase Orders7 daysWed 6/20/12Thu 6/28/12
0% Execute QA tests for Shipping Documents2 daysMon 7/9/12Tue 7/10/12
0% Execute QA tests for Reporting1 dayFri 6/29/12Fri 6/29/12
0% Execute QA tests for SKU Management2 daysWed 7/11/12Thu 7/12/12
0% Systems Integration Tests12 daysWed 6/20/12Thu 7/5/12
0% Execute SIT tests for Review/Update/Fulfill Purchase Orders7 daysWed 6/20/12Thu 6/28/12
0% Execute SIT tests for Shipping Documents2 daysTue 7/3/12Wed 7/4/12
0% Execute SIT tests for Reporting1 dayThu 7/5/12Thu 7/5/12
0% Execute SIT tests for SKU Management2 daysFri 6/29/12Mon 7/2/12
0% User Acceptance Tests15 daysWed 6/20/12Tue 7/10/12
0% Execute UAT tests for Review/Update/Fulfill Purchase Orders15 daysWed 6/20/12Tue 7/10/12
0% Execute UAT tests for Shipping Documents5 daysTue 7/3/12Mon 7/9/12
0% Execute UAT tests for Reporting5 daysThu 6/28/12Wed 7/4/12
0% Execute UAT tests for SKU Management5 daysTue 6/26/12Mon 7/2/12