UG:DR KPI Timeline
From UG
Contents |
Timeline Milestones Deadlines
May
- May 20:
- project STARTED
- May 28, Mon, 9am EST:
- 3567 DR1 : dev/QA completed and moved to SIT
- May 29, Tue, 11 am EST:
- 3567 DR1 : SIT completed and moved to UAT (demo to Marc)
- 3575 Evaluate LogiXML: Report with time estimates presented to Marc
June
- June 1, Fri, 9am EST:
- 0003583 DR2 part A: dev/QA completed and moved to SIT
- 18 / Mon
- 4pm EST: demo to Simon
- 5pm EST: Date KPI prelim design due to Marc
- 20 / Wed
- 3595 (Cost KPI, Main View): Dev completed, push to QA
- 21 / Th
- 3595: QA/bugfix completed
- Staging created at the end of the day
- 22 / Fri
- 3662 (Dates KPI): dev started
- 25 / Mon
- 3662: first panel deployed to QA
- 27 / Wed
- Release to Prod (3595)
July
- July 6 Fri, 9,10,11
- staging
- July 11 Wed
- rel 3662 into prod