Timeline Milestones Deadlines

  • May 20:
    • project STARTED
  • May 28, Mon, 9am EST:
    • 3567 DR1 : dev/QA completed and moved to SIT
  • May 29, Tue, 11 am EST:
    • 3567 DR1 : SIT completed and moved to UAT (demo to Marc)
    • 3575 Evaluate LogiXML: Report with time estimates presented to Marc
  • June 1, Fri, 9am EST:
    • 0003583 DR2 part A: dev/QA completed and moved to SIT
  • June 18, 4 pm EST
    • 4pm EST: demo to Simon
    • 5pm EST: Date KPI prelim design due to Marc
  • June 20
    • 3595 Dev completed
  • June 21 Thur
    • QA/bugfix and rel to staging end of the day
  • June 22
    • 3662 Dates KPI started dev
  • June 27 Wed
    • Prod (3595)
  • June 29
    • release of Phase 1A.1 to prod
  • July 6 Fri, 9,10,11
    • staging
  • July 11 Wed
    • rel 3662 into prod