This is a 3rd part of the article. Previous: SA re defined part 2

Weekly Status update meetings

 %BA %SA %Dev %QA %UAT %WU mantis fields

These fields indicate estimated % of task completed. Examples: 5% - just started; 100% - fully completed

Should be updated once a week before #Weekly Status update meetings

%BA - to be set by BA
%SA - to be set by SA
%Dev - to be set by Developer
%QA - to be set by QA engineer
%UAT - to be set by BA
%WU - to be set by BA