Cybertrax 2.1 Client (PM)
From UG
Contents |
About this doc
This wiki provides all Proj Management info for Cybertrax 2.1 Client project.
Project documentation
All information is gathered and structured in several wikis under Category:Cybertrax 2.1 Client
Project communication
All communication is done through:
- mantis
- Skype
All mantis tasks are under this parent: http://mantis.jaguarfreight.com/mantis/view.php?id=2077
Project team
Project business processes and tools
Project update meetings
- who must attend: Andrei, Sasha, Alex, Denise
- Tuesd, Thursd 10-11am
- Skype chat
- Coordinator on NY side / Host: Alex
- Coordinator on Kiev side: Andrei
Project broadcasts and forum
- Broadcasts / News posted into mantis: http://mantis.jaguarfreight.com/mantis/view.php?id=2127
- Questions / answers should be posted there as well or we will use wiki discussion, see http://en.wikipedia.org/wiki/SummarizeDiscussion
Project schedule
June 2010
S | M | T | W | T | F | S |
30 | 31 | 1 | 2 | 3 | 4 | 5 |
6 Staging | 7 | 8 | 9 | 10 | 11 | 12 |
13 | 14 | 15 | 16 | 17 | ||
week 1: June 7 Mon - June 11 Fri
- meetings with clients
- preliminary design sessions
- requirements: 50% done
- design: 30% done
- documentation: 10% done
- coding: 0% done
- QA: 0% done
week 2: June 14 Mon - June 18 Fri
- analyze requirements
- invent design
- write detailed documentation
- Wed 2pm: send draft to Simon, Marc
- Fri 4pm: send ver 1.0 to Bill
- requirements: 80% done
- design: 70% done
- documentation: 60% done
- coding: 5% done
- QA: 0% done
week 3: June 21 Mon - June 25 Fri
- finalize requirements
- finalize design
- improve documentation
- define tasks for every developer
- start coding and QA
- Tue 10pm: Kiev/NY status update
- Thur 10pm: Kiev/NY status update
- requirements: 95% done
- design: 90% done
- documentation: 80% done
- coding: 30% done
- QA: 20% done
week 4: June 28 Mon - July 2 Fri
- continue coding and QA
- start UC testing
- Tue 10pm: Kiev/NY status update
- Thur 10pm: Kiev/NY status update
- requirements: 99% done
- design: 99% done
- documentation: 90% done
- coding: 60% done
- QA: 50% done
week 5: July 5 Mon - July 9 Fri
- complete coding and QA
- complete UC testing
- Create User Guide, Rollout Schedule, Training Plan, Support plan
- Tue 10pm: Kiev/NY status update
- Thur 10pm: Kiev/NY status update
- documentation: 99% done
- coding: 99% done
- QA: 99% done
week 6: July 12 Mon - July 16 Fri
- QA on staging
- Release
- Mon 9am: release to Staging
- Tue 10pm: Kiev/NY status update
- Thur 10pm: Kiev/NY status update
- Thur 7-8pm: release to Production
week 7: July 19 Mon - July 23 Fri
- First week of release
- Tue 10pm: Kiev/NY status update
- Thur 10pm: Kiev/NY status update