About this doc

This wiki provides all Proj Management info for Cybertrax 2.1 Client project.

Project documentation

All information is gathered and structured in several wikis under Category:Cybertrax 2.1 Client

Project communication

All communication is done through:

  • mantis
  • Skype
  • email

All mantis tasks are under this parent: http://mantis.jaguarfreight.com/mantis/view.php?id=2077

Project team

Project business processes and tools

Project update meetings

  • who must attend: Andrei, Sasha, Alex, Denise
  • Tuesd, Thursd 10-11am
  • Skype chat
  • Coordinator on NY side / Host: Alex
  • Coordinator on Kiev side: Andrei

Project broadcasts and forum

Project schedule

week 1: June 7 Mon - June 11 Fri

  • meetings with clients
  • preliminary design sessions
  • requirements: 50% done
  • design: 30% done
  • documentation: 10% done
  • coding: 0% done
  • QA: 0% done

week 2: June 14 Mon - June 18 Fri

  • analyze requirements
  • invent design
  • write detailed documentation
  • Wed 2pm: send draft to Simon, Marc
  • Fri 4pm: send ver 1.0 to Bill
  • requirements: 80% done
  • design: 70% done
  • documentation: 60% done
  • coding: 5% done
  • QA: 0% done

week 3: June 21 Mon - June 25 Fri

  • finalize requirements
  • finalize design
  • improve documentation
  • define tasks for every developer
  • start coding and QA
  • Tue 10pm: Kiev/NY status update
  • Thur 10pm: Kiev/NY status update
  • requirements: 95% done
  • design: 90% done
  • documentation: 80% done
  • coding: 30% done
  • QA: 20% done

week 4: June 28 Mon - July 2 Fri

  • continue coding and QA
  • start UC testing
  • Tue 10pm: Kiev/NY status update
  • Thur 10pm: Kiev/NY status update
  • requirements: 99% done
  • design: 99% done
  • documentation: 90% done
  • coding: 60% done
  • QA: 50% done

week 5: July 5 Mon - July 9 Fri

  • complete coding and QA
  • complete UC testing
  • Create User Guide, Rollout Schedule, Training Plan, Support plan
  • Tue 10pm: Kiev/NY status update
  • Thur 10pm: Kiev/NY status update
  • documentation: 99% done
  • coding: 99% done
  • QA: 99% done

week 6: July 12 Mon - July 16 Fri

  • QA on staging
  • Release
  • Mon 9am: release to Staging
  • Tue 10pm: Kiev/NY status update
  • Thur 10pm: Kiev/NY status update
  • Thur 7-8pm: release to Production

week 7: July 19 Mon - July 23 Fri

  • First week of release
  • Tue 10pm: Kiev/NY status update
  • Thur 10pm: Kiev/NY status update

Project plan and do list