UG:DR KPI Timeline

From UG

Revision as of 16:34, 20 June 2012 by Alex (Talk | contribs)
Jump to: navigation, search


Contents

Timeline Milestones Deadlines

May

  • May 20:
    • project STARTED
  • May 28, Mon, 9am EST:
    • 3567 DR1 : dev/QA completed and moved to SIT
  • May 29, Tue, 11 am EST:
    • 3567 DR1 : SIT completed and moved to UAT (demo to Marc)
    • 3575 Evaluate LogiXML: Report with time estimates presented to Marc

June

  • June 1, Fri, 9am EST:
    • 0003583 DR2 part A: dev/QA completed and moved to SIT
  • 18 / Mon
    • 4pm EST: demo to Simon
    • 5pm EST: Date KPI prelim design due to Marc
  • 20 / Wed
    • 3595 (Cost KPI, Main View): Dev completed, push to QA
  • 21 / Th
    • 3595: QA/bugfix completed
    • Staging created at the end of the day
  • 22 / Fri
    • 3662 (Dates KPI): dev started
  • 25 / Mon
    • 3662: first panel deployed to QA
  • 27 / Wed
    • Release to Prod (3595)

July

  • July 6 Fri, 9,10,11
    • staging
  • July 11 Wed
    • rel 3662 into prod