2011 Feb Sprint

From UG

Revision as of 15:23, 3 March 2011 by Montira (Talk | contribs)
Jump to: navigation, search


Contents

Intro

Feb 2011 sprint plan:

  • Staging Release: March 7, 2011
  • Production Release: March 10, 2011

Original spreadsheet can be found: 2768

Feb Sprint Plan

File:ResourceMarch10.JPG File:FebDevSprintPlan1.JPG

Weekly updated Plan Feb 10

File:Feb10.JPG

Note: Task 2759 was added on Monday Feb 7 for an urgent bug that was needed to be resolved and required Emer Rel.

Emergency Release was happened on Tuesday Feb 8 at 6 PM (NY time)

Weekly updated Plan Feb 17

NOTE: 2 tasks have been added into this sprint:

  • 2759 [ClientSP ph3] Bug: Cannot find 2 delivered CT records in both internal & client application
  • 2771 Add addtional text content on dispatch confirmation email (Truck Dom - Web portal)

These 2 tasks are released to production during the sprint plan. Feb 8 and 11.

    • One additional major interruption for Misha and Sasha...is the same dispatched email that keep sending, some of the dispatched emails is not sending out. Conclusion: Descartes has to fix this issue. Our Dev can only manually delete the files...but this is out of control. THis should be control from Descartes system!

File:Feb17.JPG

Weekly updated Plan Feb 24

NOTE: Tasks have been added and cut on this sprint.

  • 2779 is added on the plan but statusX for now since it is pending for Marc approval
  • 2781 is a BUG- need to be added on the plan to be fixed
  • 2783 is a BUG- need to be added on the plan to be fixed
  • 1520 was added then cut from this sprint, because at first Karen needed this task, but later on Simon disapproved it, so Kostya has to roll it back (StatusX for now)

File:Feb24Sprint.JPG

Weekly updated Plan March 3

File:FebSprintPlanMarch3Updated.JPG

Weekly updated Plan March 10