2011 Feb Sprint
From UG
Contents |
Intro
Feb 2011 sprint plan:
- Staging Release: March 7, 2011
- Production Release: March 10, 2011
Original spreadsheet can be found: 2768
Feb Sprint Plan
Weekly updated Plan Feb 10
Note: Task 2759 was added on Monday Feb 7 for an urgent bug that was needed to be resolved and required Emer Rel.
Emergency Release was happened on Tuesday Feb 8 at 6 PM (NY time)
Weekly updated Plan Feb 17
NOTE: 2 tasks have been added into this sprint:
- 2759 [ClientSP ph3] Bug: Cannot find 2 delivered CT records in both internal & client application
- 2771 Add addtional text content on dispatch confirmation email (Truck Dom - Web portal)
These 2 tasks are released to production during the sprint plan. Feb 8 and 11.
- One additional major interruption for Misha and Sasha...is the same dispatched email that keep sending, some of the dispatched emails is not sending out. Conclusion: Descartes has to fix this issue. Our Dev can only manually delete the files...but this is out of control. THis should be control from Descartes system!