SA re defined part 3
From UG
Contents |
Intro
This is a 3rd part of the article. Previous: SA re defined part 2
Monthly BA and SA planning process
I introduce monthly plans for BAs and SAs.
See examples under Category:Proj Plans
Weekly Status update
Once a week everyone should update task status. Steps:
- BA, SA, Developer, QA must update %Percent Complete mantis fields
- BA must post updated spreadsheets into Category:Proj Plans and email to management
- request meeting (if required) to resolve potential problems
Percent Complete mantis fields
These fields indicate estimated % of task completed. Examples: 5% - just started; 100% - fully completed
Should be updated once a week before #Weekly Status update meetings.
%BA - to be set by BA %SA - to be set by SA %Dev - to be set by Developer %QA - to be set by QA engineer %UAT - to be set by BA %WU - to be set by BA