PM process
From UG
Contents |
[edit] Intro
[edit] Lead PM
[edit] End of the week updates
PM sends weekly update to Lead PM on their projects.
Lead PM sends weekly update to the President, cc others.
[edit] Meeting notes
[edit] Phases
[edit] Init
- project gets assigned to PM by Lead PM through Mantis
- meet with Lead PM
- create initial version of Proj Plan
- research subject matter
[edit] BA/SA
- assign BA/SA
- organize project kick off meeting (present plan, explain responsibilities, etc)
- create proj plan that covers BA/SA phase (with milestones and dates)
- Milestone: Review design with MO
[edit] Dev/QA/UAT
- once initial BA work completed assign Dev Manager
- have a meeting with Development Manger
- create Work breakdown structure (with Development Manger)
- create preliminary proj plan for Dev/QA phase (with Development Manger)
- create team / resource allocation (with Development Manger)
- organize project kick off meeting (present plan, explain responsibilities, etc)
[edit] Close
- organise project post mortem - analysis of bad and good
[edit] Ongoing Activities
- get regular project status updates from team (2 times a week)
- update Chief PM (once a week)
- resolve conflicts, delays, risks, issues, etc
- if proj plan has changed - distribute updated
[edit] Standard methods
[edit] Communication
All communication is done through:
- mantis
- Skype
- email (everyone must check min 2 times a day and reply or at least confirm e-mail received same day)