CT2 Resources Demand Supply Allocation
From UG
(→Ops Component) |
(→2010 June to December Forecast) |
||
Line 109: | Line 109: | ||
* potentially adding additional fields and features to support above | * potentially adding additional fields and features to support above | ||
- | * | + | * Estimates |
** start: mid June | ** start: mid June | ||
- | ** length: 1- | + | ** length: 1-3 month |
- | * emh = | + | ** emh low = 20 per week |
+ | ** emh high = 40 per week | ||
==== Trucking Domestic Optimization (TMS features) ==== | ==== Trucking Domestic Optimization (TMS features) ==== | ||
Line 118: | Line 119: | ||
Jaguar plans to add a number of complex TMS features to CT2 | Jaguar plans to add a number of complex TMS features to CT2 | ||
- | * | + | * Estimates |
** start: July-September | ** start: July-September | ||
** length: 6-12 months | ** length: 6-12 months | ||
- | * emh = | + | ** emh low = 20 per week |
+ | ** emh high = 40 per week | ||
==== Rates Interface ==== | ==== Rates Interface ==== | ||
Line 127: | Line 129: | ||
Jaguar plans to add Rates Interface. | Jaguar plans to add Rates Interface. | ||
- | * | + | * Estimates |
** start: July-September | ** start: July-September | ||
- | ** length: 2- | + | ** length: 2-3 months |
- | * emh = | + | ** emh low = 20 per week |
+ | ** emh high = 40 per week | ||
==== EDI ==== | ==== EDI ==== | ||
Line 136: | Line 139: | ||
Jaguar plans to integrate with Clients, Vendors, etc through EDI (for example receive Traffic Sheets, send Invoices) | Jaguar plans to integrate with Clients, Vendors, etc through EDI (for example receive Traffic Sheets, send Invoices) | ||
- | * | + | * Estimates |
** start: asap | ** start: asap | ||
** length: TBD | ** length: TBD | ||
- | * emh = | + | ** emh low = 20 per week |
+ | ** emh high = 40 per week | ||
==== Inventory Management ==== | ==== Inventory Management ==== | ||
Line 145: | Line 149: | ||
Jaguar plans to create Inventory Management components (as a CT2 feature or stand alone application) | Jaguar plans to create Inventory Management components (as a CT2 feature or stand alone application) | ||
- | * | + | * Estimates |
** start: TBD | ** start: TBD | ||
** length: TBD | ** length: TBD | ||
- | * emh = | + | ** emh low = 20 per week |
+ | ** emh high = 40 per week | ||
==== www.jaguarfreight.com website re-design ==== | ==== www.jaguarfreight.com website re-design ==== | ||
Line 154: | Line 159: | ||
Jaguar plans to integrate with Clients, Vendors, etc through EDI (for example receive Traffic Sheets, send Invoices) | Jaguar plans to integrate with Clients, Vendors, etc through EDI (for example receive Traffic Sheets, send Invoices) | ||
- | * | + | * Estimates |
** start: asap | ** start: asap | ||
** length: TBD | ** length: TBD | ||
- | * emh = | + | ** emh low = 20 per week |
+ | ** emh high = 40 per week | ||
=== Etc === | === Etc === |
Revision as of 17:49, 17 May 2010
This article is about Demand for CT2 features and related Supply / Allocation of Human Resources.
We need to build smart Supply Chain for Software Development! ))
Contents |
Metrics
There are 2 types of activities:
- continuous: bugfix, tweaking (small to medium changes)
- projects
ftl
It is proposed to use ftl (full time load) unit of measurement. This is to measure demand for IT staff (SAs, BAs, developers, QAs, Support Engineers).
Assumptions:
- One full time employee works 8 m/h a day ~ 40 m/h a week ~ 160 m/h a month
- One Sprint ~ One month
The following metrics are suggested:
full load
- 1 ftl (full load)
- if average numb of hours required: 30 to 40 per week ~ 120-160 per month
medium load
- 3/4 ftl (med load)
- if average numb of hours required: 20 to 30 per week ~ 80-120 per month
low load
- 1/2 ftl (low load)
- if average numb of hours required: 10 to 20 per week ~ 40-80 per month
very low load
- 1/4 ftl (very low load)
- if average numb of hours required: 1 to 10 per week ~ 4-40 per month
2010 June to December Forecast
Existing modules
Acc Component
- continuous bug-fix/tweaking:
- emh low = 5 per week
- emh high = 10 per week
- project 1) Re-design cost mapping and P&L for CTs, Groups, Masters
- emh = TBD
- deadline: asap
- project 2) see Category:Salesman
- emh = TBD
- deadline: asap
Client Component
- continuous bug-fix/tweaking:
- emh low = 10 per week
- emh high = 30 per week
- project 1) see #0001707 Replace Skype with our own Instant Messaging feature
- emh = TBD
- deadline: asap
- project 2) see #0001999 Create Agent Interface component/application
- emh = TBD
- deadline: asap
Ops Component
- continuous bug-fix/tweaking:
- emh low = 20 per week
- emh high = 40 per week (could be even more)
- projects: TBD
- emh = TBD
Ops Pdfs Component
- continuous bug-fix/tweaking:
- emh low = 10 per week (will be getting lower soon)
- emh high = 20 per week (will be getting lower soon)
- projects: TBD
- emh = TBD
Ops Reps Component
- continuous bug-fix/tweaking:
- emh low = 10 per week (will be getting lower soon)
- emh high = 30 per week (will be lower if no new reports requested)
- projects: #0001998 Have all CT fields available on all CT reports
- emh = TBD
New Modules
Integration with TMS
Jaguar is planning to purchase a large TMS system that has to be integrated with CT2. This would mean:
- supporting real time integration / flow of data between 2 systems (one or both directions)
- potentially adding additional fields and features to support above
- Estimates
- start: mid June
- length: 1-3 month
- emh low = 20 per week
- emh high = 40 per week
Trucking Domestic Optimization (TMS features)
Jaguar plans to add a number of complex TMS features to CT2
- Estimates
- start: July-September
- length: 6-12 months
- emh low = 20 per week
- emh high = 40 per week
Rates Interface
Jaguar plans to add Rates Interface.
- Estimates
- start: July-September
- length: 2-3 months
- emh low = 20 per week
- emh high = 40 per week
EDI
Jaguar plans to integrate with Clients, Vendors, etc through EDI (for example receive Traffic Sheets, send Invoices)
- Estimates
- start: asap
- length: TBD
- emh low = 20 per week
- emh high = 40 per week
Inventory Management
Jaguar plans to create Inventory Management components (as a CT2 feature or stand alone application)
- Estimates
- start: TBD
- length: TBD
- emh low = 20 per week
- emh high = 40 per week
www.jaguarfreight.com website re-design
Jaguar plans to integrate with Clients, Vendors, etc through EDI (for example receive Traffic Sheets, send Invoices)
- Estimates
- start: asap
- length: TBD
- emh low = 20 per week
- emh high = 40 per week
Etc
Misc
Development based on Requirements not Detailed Design
2 possible options:
- Remote Developer (programmer) creates detailed design based on requirements
- Remote Designer creates detailed design based on requirements
Both options would increase numb of hours required in Remote Team