ASN 20 Timeline
From UG
(Difference between revisions)
Alex (Talk | contribs)
(Created page with 'Category:ASN 20 == 2012 == === July === * July 1: ** project STARTED *** (scope/approach was reduced from ASN/I-Portal to fast track strictly ASN 2.0) *** Alex took over …')
Newer edit →
(Created page with 'Category:ASN 20 == 2012 == === July === * July 1: ** project STARTED *** (scope/approach was reduced from ASN/I-Portal to fast track strictly ASN 2.0) *** Alex took over …')
Newer edit →
Revision as of 20:02, 9 August 2012
Contents |
2012
July
- July 1:
- project STARTED
- (scope/approach was reduced from ASN/I-Portal to fast track strictly ASN 2.0)
- Alex took over this project from Tira
- project STARTED
- July 1 - July 13 (2 weeks):
- Requirements Phase - completed
- July 16 - 20 (1 week):
- Elco visit + Alex's PTO
- July 23 - Aug 3 (2 weeks):
- Solution (Architecture/Design) Phase - completed
August
Week of Aug 6 to 10
- Mon, 6: Review of Solution (Marc/Alex), collecting feedback (significant changes requested)
- Mon-Fri: work on Final Version
Week of Aug 13 to 17
- Mon:
- Final version of Solution completed and disseminated
- Suggested Breakdown of Tasks disseminated
- Tue:
- Breakdown of Tasks approved
- Mantises created; developers assigned for estimation
- Fri:
- Tasks estimated
- Project Schedule / Release Date adjusted accordingly to estimates