UG:IP2 Timeline

From UG

(Difference between revisions)
Jump to: navigation, search
(About)
(About)
Line 5: Line 5:
This wiki contains all important events associated with software development associated with a given project.
This wiki contains all important events associated with software development associated with a given project.
-
'''In bold''' are events that are of interested to the Product Team (Marc/Simon).
+
'''In bold''' are events that are of interest to the Product Team (Marc/Simon).
== 2012 ==
== 2012 ==

Revision as of 21:15, 27 June 2012


Contents

About

This wiki contains all important events associated with software development associated with a given project.

In bold are events that are of interest to the Product Team (Marc/Simon).

2012

July

  • 13 / Fri
    • Timeline will be converted from L0 (initial) to L1 (fine) estimates
  • 26 / Th
    • Shipper module: release to UAT

Aug

  • 23 / Th
    • Planner module: release to UAT

Sep

  • 27 / Th
    • Jaguar module: release to UAT

Oct

  • 25 / Th
    • Misc module: release to UAT

Nov

  • TBD
    • Release to prod

Dec