UG:DR KPI Timeline
From UG
(Difference between revisions)
(→July) |
(→June) |
||
Line 15: | Line 15: | ||
=== June === | === June === | ||
- | * | + | * 1 / Fri |
- | ** | + | ** 9am EST: 3583 (DR2 part A): dev/QA completed and moved to SIT |
* 18 / Mon | * 18 / Mon | ||
- | ** 4pm EST: demo to Simon | + | ** 4pm EST: 3595 (Cost KPI) Marc demo to Simon |
- | ** 5pm EST: Date KPI prelim design due to Marc | + | ** 5pm EST: 3662 (Date KPI): prelim design due to Marc |
* 20 / Wed | * 20 / Wed |
Revision as of 16:58, 20 June 2012
Contents |
Timeline Milestones Deadlines
May
- May 20:
- project STARTED
- May 28, Mon, 9am EST:
- 3567 DR1 : dev/QA completed and moved to SIT
- May 29, Tue, 11 am EST:
- 3567 DR1 : SIT completed and moved to UAT (demo to Marc)
- 3575 Evaluate LogiXML: Report with time estimates presented to Marc
June
- 1 / Fri
- 9am EST: 3583 (DR2 part A): dev/QA completed and moved to SIT
- 18 / Mon
- 4pm EST: 3595 (Cost KPI) Marc demo to Simon
- 5pm EST: 3662 (Date KPI): prelim design due to Marc
- 20 / Wed
- 3595 (Cost KPI): Dev completed, push to QA
- 3662 (Dates KPI): spec completed, accepted by dev
- 21 / Th
- 3595 (Cost KPI): QA/bugfix completed
- Staging created at the end of the day
- 22 / Fri
- 3662 (Dates KPI): dev started
- 25 / Mon
- 3662 (Dates KPI): 1st release to QA/SIT
- 27 / Wed
- Release to Prod (3595 Cost KPI)
- 28 / Thur
- 3662 (Dates KPI): 2nd release to QA/SIT; release to UAT1
July
- 2 / Mon
- 3662 (Dates KPI): 3rd release to QA/SIT
- 5 / Th
- 3662 (Dates KPI): 4th release to QA/SIT; release to UAT2
- 3662 (Dates KPI): dev/bugfix completed
- 6 / Fri
- Staging started (morning kiev time)
- 11 / Wed
- Release to Prod: 3662 (Dates KPI)