Dev News 2011

From UG

(Difference between revisions)
Jump to: navigation, search
(Detailed example of monthly project plan to be created and maintained by BAs)
(Detailed example of BA monthly project plan)
Line 50: Line 50:
=== Detailed example of BA monthly project plan ===
=== Detailed example of BA monthly project plan ===
-
* MUST to be created at the beginning of sprint and sent to me for review
+
* MUST be created at the beginning of sprint and sent to me for review
* Please use format below.   
* Please use format below.   

Revision as of 16:28, 12 April 2011


Contents

Intro

At the moment this is a collection of 2011 messages from Dev Director to the team related to dev biz process, announcements, etc

Last year messages: Dev News

Jan 3

See 2011 January 3 update

Jan 31

See 2010 Jan 31: Impact of IT transformation

Apr 11

Updated BA process

See Figure below.

File:No SA process.jpg

Focus on Requirements not Design, direct BA to Dev interaction, Prototype if required

Highlights of new process:

  • Focus on Requirements not Design
  • direct BA to Dev interaction
  • Prototype if required

BA Management and updates

I would like BAs to be as independent is possible (work with little supervision).

This means that after they receive BA Sprint Plan from CT2 Board (list of projects and tasks) they create more detailed plans for themselves and work independently only providing weekly status updates in the form of short written report and meeting (if required), once at the end of each week.

Example of BA monthly plan:

File:Example of BA monthly plan.JPG


Example of BA weekly report:

TBD

Apr 12

Detailed example of BA monthly project plan

  • MUST be created at the beginning of sprint and sent to me for review
  • Please use format below.


NOTE1: You can use additional tabs (one per project for example) if more convenient.

NOTE2: Original xls can be downloaded from here: http://ct.jaguarfreight.com/mantis/file_download.php?file_id=2180&type=bug

File:Project plan example.JPG