Tira
From UG
(Difference between revisions)
(→Feb 2011 Plan) |
(→Feb 2011 Plan) |
||
Line 41: | Line 41: | ||
* Plans for Feb Dev Sprint plan (monitoring/updating/Analysis) | * Plans for Feb Dev Sprint plan (monitoring/updating/Analysis) | ||
* Plans for Feb BA/SA Sprint plan | * Plans for Feb BA/SA Sprint plan | ||
+ | |||
+ | ==== UAT plan ==== |
Revision as of 22:19, 16 February 2011
Contents |
About
Dec 2010
Dec 2010 Plan
Main Plan for EA enhancement: See attached spreadsheet from here here
Additional plan: see spreadsheet from here
Jan 2011 Plan
Create 2 proposals to submit to EA for these 3 tasks below. Plan links to mantis 2687
Jan 13 weekly update
Jan 20 weekly update
New tasks have been gradually added.
Jan 27 weekly update
Feb 3 weekly update
Feb 2011 Plan
- Meeting with Marc for EA & CEI requirements (Marc was on site Feb 3, 2011)
- Meeting with Marc, Alex, Karen, Tracie for Rate Database
- Meeting with Alex, Denise, Tracie for TM Rate database
- Meeting with Alex, Tracie, Alexis, and Misha for Air Status and EU Adv Notice project
- Knowledge exchanges
- Brainstorming requirements for rate database and TM rate database issue
- Support TMS issue (Corrupted XML)
- Plans for Feb Dev Sprint plan (monitoring/updating/Analysis)
- Plans for Feb BA/SA Sprint plan