(Created page with 'Category: News == Changes in Jan 2011 == * New structure: see SDM 2010 2011 * Tira is appointed to be a team lead of Product And Support Team * see allocation changes …')
Newer edit →

Revision as of 19:47, 3 January 2011


Contents

Changes in Jan 2011

BASA Sprint

  • Managed by Tira
  • It is a monthly Sprint for Product Team (BA/SA work)
  • see BASA Sprint mantis project
    • View Issues should have these columns:
Project	BASAspr#	Status	T	p.BA	p.SA	p.Dev	%BA	%SA	comp	  	  	ID	Summary
  • new related mantis fields:
    • BASAspr#
    •  %BA
    •  %SA

New Rules for Dev Sprint

  • Managed by Alex for now
  • Interface to Product Team processes and BASA Sprint managed by Tira
  • 1) normal sprint should has 4 full weeks of development starting on Monday and ending on Fri
    • it is OK to have 1-2 national holidays or days off to be a part of a Sprint, if more consider adding one additional week to Sprint
  • 2) Staging/Dev Est week is not considered part of the Sprint. During this week:

Allocation per module for Jan 2011

NOTE: Roma is again dedicated QA

(Module / BA / SA(QA)):


  • Category:OpsAdmin / ? / Alex OR Andrei (Roma)
  • Inventory / ? / Alex OR Andrei (Roma)