Monthly parent for tweaks and bugs

From UG

(Difference between revisions)
Jump to: navigation, search
(Note B)
 
Line 6: Line 6:
  [*11 Deni] .... <proj>
  [*11 Deni] .... <proj>
-
This is a parent for all non-project (stand alone tasks) which Denise is handling and plans to complete in Nov 2010:
+
This is a [[mantis parent]] for all non-project (stand alone tasks) which Denise is handling and plans to complete in Nov 2010:
a) "tweaks" (BA work)
a) "tweaks" (BA work)
b) "bugs" (Support work)
b) "bugs" (Support work)
 +
 +
=== Note 1 ===
 +
'''Also pls add a link in a Relationships to all projects that are active this month (some work will be done).'''
== Rules ==
== Rules ==
Line 36: Line 39:
Ideally 90% + of these BA-tasks should pass BA same month and started under SA; bugs-resolved same month
Ideally 90% + of these BA-tasks should pass BA same month and started under SA; bugs-resolved same month
 +
 +
== History ==
 +
 +
* first version created
 +
* [[#Note 1]] added

Current revision as of 06:51, 14 November 2010


Contents

[edit] Intro

Every month we shall create a parent project like below.

[*11 Deni] .... <proj>

This is a mantis parent for all non-project (stand alone tasks) which Denise is handling and plans to complete in Nov 2010:

a) "tweaks" (BA work)

b) "bugs" (Support work)

[edit] Note 1

Also pls add a link in a Relationships to all projects that are active this month (some work will be done).

[edit] Rules

! Tasks that are already listed under projects should not be listed here.

! Set "projID" on each of child tasks to "*11 Deni" (for example above)

[edit] Note A

This type of project parent mantis and concept replaced the one used to be called "Nov Dec Twks"

[edit] Note B

Mantises created for november:

0002540	?	*11 Alex	[*11 Alex] .... <proj>
0002548	?	*11 Denise	[*11 Denise] .... <proj>
0002524	?       *11 Tira	[*11 Tira] ......... <proj>
0002549	?       *11 Tracie	[*11 Tracie] ...... <proj>

[edit] Purpose

This mechanism should help everyone to track BA/Support tasks that are not under projects.

Ideally 90% + of these BA-tasks should pass BA same month and started under SA; bugs-resolved same month

[edit] History

  • first version created
  • #Note 1 added