CT2 Development Process
From UG
(→Overview) |
(→Software Development (Vendor) team) |
||
Line 39: | Line 39: | ||
* manages resources | * manages resources | ||
* manages detailed development schedule that includes development, bugfix, QA, graphics | * manages detailed development schedule that includes development, bugfix, QA, graphics | ||
+ | * gets regular updates from developer, QA, graphic designer regarding deadlines | ||
+ | * if there is a chance for ETA to be postponed then he immediately notifies Project Manager and they both decide what to do: move tasks around, add resources or push ETA forward | ||
'''QA engineer''' | '''QA engineer''' | ||
Line 45: | Line 47: | ||
* runs test plans | * runs test plans | ||
* forwards bugs to developer | * forwards bugs to developer | ||
+ | * provides ETA for his work to '''Development Lead''' | ||
+ | * must immedialy notify '''Development Lead''' if his ETA can slip | ||
'''developer''' | '''developer''' | ||
* makes sure specs are complete | * makes sure specs are complete | ||
* implements new sub-components, changes, tweaks, bug fixes | * implements new sub-components, changes, tweaks, bug fixes | ||
+ | * deploy, forwards his work to QA | ||
+ | * provides ETA for his work to '''Development Lead''' | ||
+ | * must immedialy notify '''Development Lead''' if his ETA can slip | ||
+ | ''' graphic designer''' | ||
- | |||
- | + | == timeboxing == | |
- | + | == scoping == | |
[[Category:PM]] | [[Category:PM]] |
Revision as of 03:50, 23 July 2009
This article defines what methodology, roles, workflow, etc we use.
Contents |
Overview
CT2 System consists of CT2 components (Client App, Ops, OpsReps, Acc. etc).
We developmen each component separately. It has its own team, project plan, etc.
Methodology
We use our own methodology that is influenced by Scrum, Agile, Waterfall, Mantis, Outsourcing.
(in italic example given for Client App component)
Users
Future users of CT2 - operators, management, etc. (non jag operators and management)
Business (Client/Sponsor) Team
Acceptance board (demo meeting) - group of people who makes final decision about acceptance, tweaks, course of the project. (sometimes Simon alone, sometimes Simon, Marc, Alex, Tira together)
Biz analyst/architect - biz expert (Simon)
- invents detailed biz requirements for the component
- transfers these requirements to Sys Analyst
Sys analyst/Architect - IT expert (Tira)
- translates detailed biz requirements into specs
- transfers specs to development team
Project manager - time/scope management expert (Tira)
- accountable for reaching the stated project objectives
- managing high level of proj plan
Software Development (Vendor) team
Development Lead - leader of the development team (Slava)
- coordinates development effort
- manages resources
- manages detailed development schedule that includes development, bugfix, QA, graphics
- gets regular updates from developer, QA, graphic designer regarding deadlines
- if there is a chance for ETA to be postponed then he immediately notifies Project Manager and they both decide what to do: move tasks around, add resources or push ETA forward
QA engineer
- makes sure that specs are complete
- creates test plans
- runs test plans
- forwards bugs to developer
- provides ETA for his work to Development Lead
- must immedialy notify Development Lead if his ETA can slip
developer
- makes sure specs are complete
- implements new sub-components, changes, tweaks, bug fixes
- deploy, forwards his work to QA
- provides ETA for his work to Development Lead
- must immedialy notify Development Lead if his ETA can slip
graphic designer