Year 2012
About
Written by SA responsible for project (Alex). To reflect and learn.
Aug
Aug 10 Fri
- requested 1 more week to add to construction
- Crash and Baseline proj plans were sent to Simon
- both allocate 4 weeks for coding
- completed Solution wiki; printing, reading, minor edits