Option 1 (crash - with new developers added and more aggressive schedules) | Option 1 (crash - with new developers added and more aggressive schedules) | ||
- | Construction 8/20/12 - 9/7/12 | + | Construction 8/20/12 - 9/7/12 days=15 Sasha, AK |
- | Verif-n (UAT) 9/10/12 - 9/21/12 | + | Verif-n (UAT) 9/10/12 - 9/21/12 days=10 Sasha, Roma, AG, New Dev 2 (as QA) |
- | Buffer 9/24/12 - 10/5/12 | + | Buffer 9/24/12 - 10/5/12 days=10 Sasha, Roma, AG |
+ | |||
Option 2 (baseline) | Option 2 (baseline) | ||
- | Construction 8/20/12 - 9/7/12 days=15 | + | Construction 8/20/12 - 9/7/12 days=15 Sasha, AK |
- | Verification 9/10/12 - 9/28/12 days=15 | + | Verification 9/10/12 - 9/28/12 days=15 Sasha, Roma, AG |
- | Buffer 10/1/12 - 10/19/12 days=15 | + | Buffer 10/1/12 - 10/19/12 days=15 Sasha, Roma, AG |
Revision as of 20:54, 9 August 2012
Contents |
2012
July
- July 1:
- project STARTED
- (scope/approach was reduced from ASN/I-Portal to fast track strictly ASN 2.0)
- Alex took over this project from Tira
- project STARTED
- July 1 - July 13 (2 weeks):
- Requirements Phase - completed
- July 16 - 20 (1 week):
- Elco visit + Alex's PTO
- July 23 - Aug 3 (2 weeks):
- Solution (Architecture/Design) Phase - completed
August
Week of Aug 6 to 10
- Mon, 6: Review of Solution (Marc/Alex), collecting feedback (significant changes requested)
- Mon-Fri: work on Final Version
Week of Aug 13 to 17
- Mon:
- Final version of Solution completed and disseminated
- Suggested WBS Work Breakdown Structure disseminated
- Tue:
- WBS approved
- Mantises created; developers assigned for estimation
- Fri:
- Tasks estimated
- Project Schedule / Release Date adjusted accordingly to estimates
Week of Aug 20 to 24
1st week of Construction/QA.
L0 Schedule per Perry
Option 1 (crash - with new developers added and more aggressive schedules)
Construction 8/20/12 - 9/7/12 days=15 Sasha, AK Verif-n (UAT) 9/10/12 - 9/21/12 days=10 Sasha, Roma, AG, New Dev 2 (as QA) Buffer 9/24/12 - 10/5/12 days=10 Sasha, Roma, AG
Option 2 (baseline)
Construction 8/20/12 - 9/7/12 days=15 Sasha, AK Verification 9/10/12 - 9/28/12 days=15 Sasha, Roma, AG Buffer 10/1/12 - 10/19/12 days=15 Sasha, Roma, AG