ASN 20 Timeline

From UG

(Difference between revisions)
Jump to: navigation, search
(Created page with 'Category:ASN 20 == 2012 == === July === * July 1: ** project STARTED *** (scope/approach was reduced from ASN/I-Portal to fast track strictly ASN 2.0) *** Alex took over …')
(Week of Aug 13 to 17)
Line 37: Line 37:
** Tasks estimated
** Tasks estimated
** Project Schedule / Release Date adjusted accordingly to estimates
** Project Schedule / Release Date adjusted accordingly to estimates
 +
 +
== L0 Schedule per Perry ==
 +
 +
Construction 8/20/12 - 9/7/12   days=15
 +
Verification 9/10/12 - 9/21/12   days=10
 +
Buffer        9/24/12 - 10/5/12   days=10

Revision as of 20:07, 9 August 2012


Contents

2012

July

  • July 1:
    • project STARTED
      • (scope/approach was reduced from ASN/I-Portal to fast track strictly ASN 2.0)
      • Alex took over this project from Tira
  • July 1 - July 13 (2 weeks):
    • Requirements Phase - completed
  • July 16 - 20 (1 week):
    • Elco visit + Alex's PTO
  • July 23 - Aug 3 (2 weeks):
    • Solution (Architecture/Design) Phase - completed

August

Week of Aug 6 to 10

  • Mon, 6: Review of Solution (Marc/Alex), collecting feedback (significant changes requested)
  • Mon-Fri: work on Final Version

Week of Aug 13 to 17

  • Mon:
    • Final version of Solution completed and disseminated
    • Suggested Breakdown of Tasks disseminated
  • Tue:
    • Breakdown of Tasks approved
    • Mantises created; developers assigned for estimation
  • Fri:
    • Tasks estimated
    • Project Schedule / Release Date adjusted accordingly to estimates

L0 Schedule per Perry

Construction	8/20/12	- 9/7/12	   days=15
Verification	9/10/12	- 9/21/12	   days=10
Buffer         9/24/12	- 10/5/12	   days=10