UG:IP2 Timeline

From UG

(Difference between revisions)
Jump to: navigation, search
(Nov)
(2012)
Line 8: Line 8:
== 2012 ==
== 2012 ==
 +
 +
'''IMPORTANT NOTE:''' This timeline is based on L0 (initial) estimates. It has a high margin of error (+/- 50 %).
=== July ===
=== July ===

Revision as of 21:18, 27 June 2012


Contents

About

This wiki contains all important events associated with software development associated with a given project.

In bold are events that are of interest to the Product Team (Marc/Simon).

2012

IMPORTANT NOTE: This timeline is based on L0 (initial) estimates. It has a high margin of error (+/- 50 %).

July

  • 13 / Fri
    • Timeline will be converted from L0 (initial) to L1 (fine) estimates
  • 26 / Th
    • Shipper module: release to UAT

Aug

  • 23 / Th
    • Planner module: release to UAT

Sep

  • 27 / Th
    • Jaguar module: release to UAT

Oct

  • 25 / Th
    • Misc module: release to UAT

Nov

  • TBD
    • All modules: Release to production

Dec

Personal tools