UG:DR KPI Timeline
From UG
(Difference between revisions)
(→Timeline Milestones Deadlines) |
(→Timeline Milestones Deadlines) |
||
Line 20: | Line 20: | ||
** 4pm EST: demo to Simon | ** 4pm EST: demo to Simon | ||
** 5pm EST: Date KPI prelim design due to Marc | ** 5pm EST: Date KPI prelim design due to Marc | ||
+ | |||
+ | * June 20 | ||
+ | ** 3595 Dev completed | ||
+ | |||
+ | * June 21 Thur | ||
+ | ** QA/bugfix and rel to staging end of the day | ||
+ | |||
+ | * June 22 | ||
+ | ** 3662 Dates KPI started dev | ||
+ | |||
+ | * June 27 Wed | ||
+ | ** Prod (3595) | ||
* June 29 | * June 29 | ||
** release of Phase 1A.1 to prod | ** release of Phase 1A.1 to prod | ||
+ | |||
+ | * July 6 Fri, 9,10,11 | ||
+ | ** staging | ||
+ | |||
+ | * July 11 Wed | ||
+ | ** rel 3662 into prod |
Revision as of 15:03, 20 June 2012
Timeline Milestones Deadlines
- May 20:
- project STARTED
- May 28, Mon, 9am EST:
- 3567 DR1 : dev/QA completed and moved to SIT
- May 29, Tue, 11 am EST:
- 3567 DR1 : SIT completed and moved to UAT (demo to Marc)
- 3575 Evaluate LogiXML: Report with time estimates presented to Marc
- June 1, Fri, 9am EST:
- 0003583 DR2 part A: dev/QA completed and moved to SIT
- June 18, 4 pm EST
- 4pm EST: demo to Simon
- 5pm EST: Date KPI prelim design due to Marc
- June 20
- 3595 Dev completed
- June 21 Thur
- QA/bugfix and rel to staging end of the day
- June 22
- 3662 Dates KPI started dev
- June 27 Wed
- Prod (3595)
- June 29
- release of Phase 1A.1 to prod
- July 6 Fri, 9,10,11
- staging
- July 11 Wed
- rel 3662 into prod