DQ and RFC process
From UG
(Difference between revisions)
(→DQ) |
|||
Line 1: | Line 1: | ||
[[Category:DQ]] | [[Category:DQ]] | ||
- | == | + | == Info == |
- | + | This wiki is about RFC and DQ methodology. | |
- | + | ||
== Glossary == | == Glossary == | ||
Line 13: | Line 12: | ||
* DQ = Development Queue | * DQ = Development Queue | ||
- | == | + | == Urgent Bugs == |
- | + | *U-bugs are managed by Sup Man, must be posted into mantis, estimated and fixed ASAP. Decide if they require Emerg Release. | |
+ | *Non Urgent Bugs are managed through RFC | ||
- | == Phases == | + | == RFC Phases == |
=== RFC === | === RFC === |
Revision as of 21:51, 3 June 2012
Contents |
Info
This wiki is about RFC and DQ methodology.
Glossary
- L0 (L zero) = initial/rough;
- L1 = full
- RFC = Request For Change
- DQ = Development Queue
Urgent Bugs
- U-bugs are managed by Sup Man, must be posted into mantis, estimated and fixed ASAP. Decide if they require Emerg Release.
- Non Urgent Bugs are managed through RFC
RFC Phases
RFC
- ph: RFC
- purpose: (Change Request/Biz Analysis or Bug Report)
- owner: Denise
Details:
- create mantis for requested Change or Non Urgent Bug
- Conduct and post into mantis L0 BA (requirements) or Detailed Bug Report
RFC ISA
- ph: RFC-ISA
- purpose: (Initial Sys Analysis)
- owner: Alex
Details:
- review periodically RFC records (say 5 a week)
- meet to discuss: Alex, AG, Sasha, Denise, etc (all together or in sub groups) (group might depend on the task)
- split / combine as required
- tweak summary/desc as required
- Mantis Description field should have 3 sections:
- Problem/Request
- Solution
- SOW link
- identify what is large enough to be classified as a project and tag as such
- discuss solution
- conduct and post into Mantis L0 SA
- set Dv (to "any" if possible or to specific dev)
- set L0 emh/emhR
RFC PR
- ph: RFC-PR (Product Team Review)
- owner: ???
Descr:
- review periodically tasks that completed RFC-SA (say 5 a week)
- meet to discuss requirements/solution/emh (Marc, Denise, Alex, Perry?)
- reject/approve (by Marc)
- set T
- post notes as required
RFC FSA
4) ph=RFC-FSA (Full System Analysis) // AG
- conduct L1 SA
- consult KU, SA, developers, BA as required
- create SOW
DQ
5) ph = DQ (Dev/QA/SIT/UAT/T2S/Rel phases of RFCs and Non Urgent Bugs) // Perry
- conduct weekly DQ meetings to: a) review previous week's progress b) create plans for next week
- review previous week's progress (post mortem):
- sort by due=wYY
- go task by task and see status/ph it is in (most must pass QA and be in SIT/UAT)
- send weekly review (post mortem) to all managers (Marc, KU, Ale, Den)
- create plans for next week:
- identify how many mh available from each dev next week
- sort tasks in DQ by T and create plan for each dev:
- assign mantis to dev
- set due mantis field to wXX where XX is week number
- send weekly plan to all managers (Marc, KU, Ale, Den)
- coordinate SIT/UAT and Releases of DQ