2011 Jan Sprint

From UG

(Difference between revisions)
Jump to: navigation, search
(Plan)
(Plan)
Line 12: Line 12:
NOTE: Please note that the task 2397 for Andriy was completed and be a part of Jan 6 released. It is still pending for Roma to test. Total hrs for this sprint with rmhR = '''406'''
NOTE: Please note that the task 2397 for Andriy was completed and be a part of Jan 6 released. It is still pending for Roma to test. Total hrs for this sprint with rmhR = '''406'''
 +
 +
=== Weekly updated Plan Jan 14 ===
 +
NOTE: Due date for .rmhR, it must be updated by the end of Thursday.
 +
 +
[[File:Jan13Updated.JPG]]
 +
 +
=== Weekly updated Plan Jan 21 ===
 +
NOTE: Due date for .rmhR, it must be updated by the end of Thursday.
 +
 +
 +
=== Weekly updated Plan Jan 28 ===
 +
NOTE: Due date for .rmhR, it must be updated by the end of Thursday.

Revision as of 16:58, 14 January 2011


Contents

Intro

Jan 2011 sprint plan:

  • Staging Release: Jan31, 2011
  • Production Release: Feb 3, 2011

File:ResourseFeb.JPG

Plan

File:Jan2011SprintPlan.JPG

NOTE: Please note that the task 2397 for Andriy was completed and be a part of Jan 6 released. It is still pending for Roma to test. Total hrs for this sprint with rmhR = 406

Weekly updated Plan Jan 14

NOTE: Due date for .rmhR, it must be updated by the end of Thursday.

File:Jan13Updated.JPG

Weekly updated Plan Jan 21

NOTE: Due date for .rmhR, it must be updated by the end of Thursday.


Weekly updated Plan Jan 28

NOTE: Due date for .rmhR, it must be updated by the end of Thursday.