CT2 Development Systems and HR transition 2011
From UG
(Difference between revisions)
Line 3: | Line 3: | ||
== Intro == | == Intro == | ||
- | Timeline | + | == Timeline == |
* jan 5 - 19 (or jan 31) // Paul is full time on-site | * jan 5 - 19 (or jan 31) // Paul is full time on-site | ||
** knowledge transfer of core to Alex | ** knowledge transfer of core to Alex | ||
** servers consolidation ?? | ** servers consolidation ?? | ||
- | ** transfer to Rackspace (CT1 server???) | + | ** frwd backups to CT1 instead of in house backup server |
+ | ** transfer to Rackspace or another provider ( 5-6 turnaround for Rackspace to setup; DNS updates) | ||
+ | *** (CT1 server???) CT1 runs MySQL 4, jag websites runs on Apache | ||
+ | *** combine SVN, Mantis, Wiki, CT2 Demo&staging | ||
+ | **** problem: during re-deploy to demo all apps will be | ||
+ | |||
* jan 19 (or jan 31) - date new CT2 Admin is found // Paul is contractor off site | * jan 19 (or jan 31) - date new CT2 Admin is found // Paul is contractor off site | ||
- | * | + | * date new CT2 Admin is found - date new CT2 Admin is self sufficient // Paul is available to answer questions |
+ | |||
+ | == Checklist == |
Revision as of 18:46, 6 January 2011
Intro
Timeline
- jan 5 - 19 (or jan 31) // Paul is full time on-site
- knowledge transfer of core to Alex
- servers consolidation ??
- frwd backups to CT1 instead of in house backup server
- transfer to Rackspace or another provider ( 5-6 turnaround for Rackspace to setup; DNS updates)
- (CT1 server???) CT1 runs MySQL 4, jag websites runs on Apache
- combine SVN, Mantis, Wiki, CT2 Demo&staging
- problem: during re-deploy to demo all apps will be
- jan 19 (or jan 31) - date new CT2 Admin is found // Paul is contractor off site
- date new CT2 Admin is found - date new CT2 Admin is self sufficient // Paul is available to answer questions