Timeline:
 +
 +
* jan 5 - 19 (or jan 31) // Paul is full time on-site
 +
** knowledge transfer of core to Alex
 +
** servers consolidation ??
 +
** transfer to Rackspace (CT1 server???) or another provider
 +
* jan 19 (or jan 31) - date new CT2 Admin is found // Paul is contractor off site
 +
*

Revision as of 18:30, 6 January 2011


Intro

Timeline:

  • jan 5 - 19 (or jan 31) // Paul is full time on-site
    • knowledge transfer of core to Alex
    • servers consolidation ??
    • transfer to Rackspace (CT1 server???) or another provider
  • jan 19 (or jan 31) - date new CT2 Admin is found // Paul is contractor off site