Intro
Timeline:
- jan 5 - 19 (or jan 31) // Paul is full time on-site
- knowledge transfer of core to Alex
- servers consolidation ??
- transfer to Rackspace (CT1 server???) or another provider
- jan 19 (or jan 31) - date new CT2 Admin is found // Paul is contractor off site