Cybertrax 2.1 Client (project plan)

From UG

(Difference between revisions)
Jump to: navigation, search
(week 7: July 19 Mon - July 23 Fri)
(Weekly Plan)
Line 91: Line 91:
* '''Thur 10pm:''' Kiev/NY status update
* '''Thur 10pm:''' Kiev/NY status update
* '''Thur 7-8pm:''' release to Production
* '''Thur 7-8pm:''' release to Production
-
 
-
== Weekly Plan ==
 
-
[[File:2010 summer calendar.JPG]]
 
-
 
-
=== week 1: June 7 Mon - June 11 Fri ===
 
-
* meetings with clients
 
-
* preliminary design sessions
 
-
 
-
:* requirements: 50% done
 
-
:* design: 30% done
 
-
:* documentation: 10% done
 
-
:* coding: 0% done
 
-
:* QA: 0% done
 
-
 
-
=== week 2: June 14 Mon - June 18 Fri ===
 
-
* analyze requirements
 
-
* invent design
 
-
* write detailed documentation
 
-
 
-
* '''Wed 2pm:''' send draft to Simon, Marc
 
-
* '''Fri 4pm:''' send ver 1.0 to Bill
 
-
 
-
:* requirements: 80% done
 
-
:* design: 70% done
 
-
:* documentation: 60% done
 
-
:* coding: 5% done
 
-
:* QA: 0% done
 
-
 
-
=== week 3: June 21 Mon - June 25 Fri ===
 
-
* finalize requirements
 
-
* finalize design
 
-
* improve documentation
 
-
* define tasks for every developer
 
-
* start coding and QA
 
-
 
-
* '''Tue 10pm:''' Kiev/NY status update
 
-
* '''Thur 10pm:''' Kiev/NY status update
 
-
 
-
:* requirements: 95% done
 
-
:* design: 90% done
 
-
:* documentation: 80% done
 
-
:* coding: 30% done
 
-
:* QA: 20% done
 
-
 
-
=== week 4: June 28 Mon - July 2 Fri ===
 
-
 
-
* continue coding and QA
 
-
* start UC testing
 
-
 
-
* '''Tue 10pm:''' Kiev/NY status update
 
-
* '''Thur 10pm:''' Kiev/NY status update
 
-
 
-
:* requirements: 99% done
 
-
:* design: 99% done
 
-
:* documentation: 90% done
 
-
:* coding: 60% done
 
-
:* QA: 50% done
 
-
 
-
=== week 5: July 5 Mon - July 9 Fri ===
 
-
 
-
* complete coding and QA
 
-
* complete UC testing
 
-
* Create User Guide, Rollout Schedule, Training Plan, Support plan
 
-
 
-
* '''Tue 10pm:''' Kiev/NY status update
 
-
* '''Thur 10pm:''' Kiev/NY status update
 
-
 
-
:* documentation: 99% done
 
-
:* coding: 99% done
 
-
:* QA: 99% done
 
-
 
-
=== week 6: July 12 Mon - July 16 Fri ===
 
-
 
-
* QA on staging
 
-
* Release
 
-
 
-
* '''Mon 9am:''' release to Staging
 
-
* '''Tue 10pm:''' Kiev/NY status update
 
-
* '''Thur 10pm:''' Kiev/NY status update
 
-
* '''Thur 7-8pm:''' release to Production
 
-
 
-
=== week 7: July 19 Mon - July 23 Fri ===
 
-
 
-
* First week of release
 
-
 
-
* '''Tue 10pm:''' Kiev/NY status update
 
-
* '''Thur 10pm:''' Kiev/NY status update
 

Revision as of 02:53, 20 June 2010


Contents

Intro

This project is very important therefore planning is critical.

Time vs Features vs Quality:

  • Focus of this project is to deploy minimal set of core features ASAP. As a result feature set will be reduced to minimum and quality might be average (but must not fall below reasonable level)

Summary of time allocated:

  • only 1 week for design
  • only 3 weeks for coding

Weekly Plan

File:2010 summer calendar.JPG

week 1: June 7 Mon - June 11 Fri

  • meetings with clients
  • preliminary design sessions
  • requirements: 50% done
  • design: 30% done
  • documentation: 10% done
  • coding: 0% done
  • QA: 0% done

week 2: June 14 Mon - June 18 Fri

  • analyze requirements
  • invent design
  • write detailed documentation
  • Wed 2pm: send draft to Simon, Marc
  • Fri 4pm: send ver 1.0 to Bill
  • requirements: 80% done
  • design: 70% done
  • documentation: 60% done
  • coding: 5% done
  • QA: 0% done

week 3: June 21 Mon - June 25 Fri

  • finalize requirements
  • finalize design
  • improve documentation
  • define tasks for every developer
  • start coding and QA
  • Tue 10pm: Kiev/NY status update
  • Thur 10pm: Kiev/NY status update
  • requirements: 95% done
  • design: 90% done
  • documentation: 80% done
  • coding: 30% done
  • QA: 20% done

week 4: June 28 Mon - July 2 Fri

  • continue coding and QA
  • start UC testing
  • Tue 10pm: Kiev/NY status update
  • Thur 10pm: Kiev/NY status update
  • requirements: 99% done
  • design: 99% done
  • documentation: 90% done
  • coding: 60% done
  • QA: 50% done

week 5: July 5 Mon - July 9 Fri

  • complete coding and QA
  • complete UC testing
  • Create User Guide, Rollout Schedule, Training Plan, Support plan
  • Tue 10pm: Kiev/NY status update
  • Thur 10pm: Kiev/NY status update
  • documentation: 99% done
  • coding: 99% done
  • QA: 99% done

week 6: July 12 Mon - July 16 Fri

  • QA on staging
  • Release
  • Mon 9am: release to Staging
  • Tue 10pm: Kiev/NY status update
  • Thur 10pm: Kiev/NY status update
  • Thur 7-8pm: release to Production