(Project schedule)
Line 37: Line 37:
* Broadcasts / News posted into mantis: http://mantis.jaguarfreight.com/mantis/view.php?id=2127
* Broadcasts / News posted into mantis: http://mantis.jaguarfreight.com/mantis/view.php?id=2127
* Questions / answers should be posted there as well or we will use wiki discussion, see http://en.wikipedia.org/wiki/SummarizeDiscussion
* Questions / answers should be posted there as well or we will use wiki discussion, see http://en.wikipedia.org/wiki/SummarizeDiscussion
-
 
-
== Project schedule ==
 
-
[[File:2010 summer calendar.JPG]]
 
-
 
-
=== week 1: June 7 Mon - June 11 Fri ===
 
-
* meetings with clients
 
-
* preliminary design sessions
 
-
 
-
:* requirements: 50% done
 
-
:* design: 30% done
 
-
:* documentation: 10% done
 
-
:* coding: 0% done
 
-
:* QA: 0% done
 
-
 
-
=== week 2: June 14 Mon - June 18 Fri ===
 
-
* analyze requirements
 
-
* invent design
 
-
* write detailed documentation
 
-
 
-
* '''Wed 2pm:''' send draft to Simon, Marc
 
-
* '''Fri 4pm:''' send ver 1.0 to Bill
 
-
 
-
:* requirements: 80% done
 
-
:* design: 70% done
 
-
:* documentation: 60% done
 
-
:* coding: 5% done
 
-
:* QA: 0% done
 
-
 
-
=== week 3: June 21 Mon - June 25 Fri ===
 
-
* finalize requirements
 
-
* finalize design
 
-
* improve documentation
 
-
* define tasks for every developer
 
-
* start coding and QA
 
-
 
-
* '''Tue 10pm:''' Kiev/NY status update
 
-
* '''Thur 10pm:''' Kiev/NY status update
 
-
 
-
:* requirements: 95% done
 
-
:* design: 90% done
 
-
:* documentation: 80% done
 
-
:* coding: 30% done
 
-
:* QA: 20% done
 
-
 
-
=== week 4: June 28 Mon - July 2 Fri ===
 
-
 
-
* continue coding and QA
 
-
* start UC testing
 
-
 
-
* '''Tue 10pm:''' Kiev/NY status update
 
-
* '''Thur 10pm:''' Kiev/NY status update
 
-
 
-
:* requirements: 99% done
 
-
:* design: 99% done
 
-
:* documentation: 90% done
 
-
:* coding: 60% done
 
-
:* QA: 50% done
 
-
 
-
=== week 5: July 5 Mon - July 9 Fri ===
 
-
 
-
* complete coding and QA
 
-
* complete UC testing
 
-
* Create User Guide, Rollout Schedule, Training Plan, Support plan
 
-
 
-
* '''Tue 10pm:''' Kiev/NY status update
 
-
* '''Thur 10pm:''' Kiev/NY status update
 
-
 
-
:* documentation: 99% done
 
-
:* coding: 99% done
 
-
:* QA: 99% done
 
-
 
-
=== week 6: July 12 Mon - July 16 Fri ===
 
-
 
-
* QA on staging
 
-
* Release
 
-
 
-
* '''Mon 9am:''' release to Staging
 
-
* '''Tue 10pm:''' Kiev/NY status update
 
-
* '''Thur 10pm:''' Kiev/NY status update
 
-
* '''Thur 7-8pm:''' release to Production
 
-
 
-
=== week 7: July 19 Mon - July 23 Fri ===
 
-
 
-
* First week of release
 
-
 
-
* '''Tue 10pm:''' Kiev/NY status update
 
-
* '''Thur 10pm:''' Kiev/NY status update
 
-
 
-
== Project plan and do list ==
 

Revision as of 03:34, 20 June 2010


Contents

About this doc

This wiki provides all Proj Management info for Cybertrax 2.1 Client project.

Project documentation

All information is gathered and structured in several wikis under Category:Cybertrax 2.1 Client

Project communication

All communication is done through:

  • mantis
  • Skype
  • email

All mantis tasks are under this parent: http://mantis.jaguarfreight.com/mantis/view.php?id=2077

Project team

Project business processes and tools

Project update meetings

  • who must attend: Andrei, Sasha, Alex, Denise
  • Tuesd, Thursd 10-11am
  • Skype chat
  • Coordinator on NY side / Host: Alex
  • Coordinator on Kiev side: Andrei