== Project schedule == | == Project schedule == | ||
+ | |||
=== week 1: June 7 Mon - June 11 Fri === | === week 1: June 7 Mon - June 11 Fri === | ||
* meetings with clients | * meetings with clients | ||
* preliminary design sessions | * preliminary design sessions | ||
+ | |||
+ | :* requirements: 50% done | ||
+ | :* design: 30% done | ||
+ | :* documentation: 10% done | ||
+ | :* coding: 0% done | ||
+ | :* QA: 0% done | ||
=== week 2: June 14 Mon - June 18 Fri === | === week 2: June 14 Mon - June 18 Fri === | ||
- | + | * analyze requirements | |
- | + | * invent design | |
- | + | * write detailed documentation | |
- | + | ||
- | * | + | * '''Wed 2pm:''' send draft to Simon, Marc |
- | + | * '''Fri 4pm:''' send ver 1.0 to Bill | |
- | + | ||
- | + | :* requirements: 80% done | |
- | :* requirements: | + | |
:* design: 70% done | :* design: 70% done | ||
:* documentation: 60% done | :* documentation: 60% done | ||
Line 61: | Line 65: | ||
=== week 3: June 21 Mon - June 25 Fri === | === week 3: June 21 Mon - June 25 Fri === | ||
+ | * finalize requirements | ||
+ | * finalize design | ||
+ | * improve documentation | ||
+ | * define tasks for every developer | ||
+ | * start coding and QA | ||
+ | |||
+ | * '''Tue 10pm:''' Kiev/NY status update | ||
+ | * '''Thur 10pm:''' Kiev/NY status update | ||
+ | |||
+ | :* requirements: 95% done | ||
+ | :* design: 90% done | ||
+ | :* documentation: 80% done | ||
+ | :* coding: 30% done | ||
+ | :* QA: 20% done | ||
+ | |||
=== week 4: June 28 Mon - July 2 Fri === | === week 4: June 28 Mon - July 2 Fri === | ||
Revision as of 01:47, 20 June 2010
Contents |
About this doc
This wiki provides all Proj Management info for Cybertrax 2.1 Client project.
Project documentation
All information is gathered and structured in several wikis under Category:Cybertrax 2.1 Client
Project communication
All communication is done through:
- mantis
- Skype
All mantis tasks are under this parent: http://mantis.jaguarfreight.com/mantis/view.php?id=2077
Project team
Project business processes and tools
Project update meetings
- who must attend: Andrei, Sasha, Alex, Denise
- Tuesd, Thursd 10-11am
- Skype chat
- Coordinator on NY side / Host: Alex
- Coordinator on Kiev side: Andrei
Project broadcasts and forum
- Broadcasts / News posted into mantis: http://mantis.jaguarfreight.com/mantis/view.php?id=2127
- Questions / answers should be posted there as well or we will use wiki discussion, see http://en.wikipedia.org/wiki/SummarizeDiscussion
Project schedule
week 1: June 7 Mon - June 11 Fri
- meetings with clients
- preliminary design sessions
- requirements: 50% done
- design: 30% done
- documentation: 10% done
- coding: 0% done
- QA: 0% done
week 2: June 14 Mon - June 18 Fri
- analyze requirements
- invent design
- write detailed documentation
- Wed 2pm: send draft to Simon, Marc
- Fri 4pm: send ver 1.0 to Bill
- requirements: 80% done
- design: 70% done
- documentation: 60% done
- coding: 5% done
- QA: 0% done
week 3: June 21 Mon - June 25 Fri
- finalize requirements
- finalize design
- improve documentation
- define tasks for every developer
- start coding and QA
- Tue 10pm: Kiev/NY status update
- Thur 10pm: Kiev/NY status update
- requirements: 95% done
- design: 90% done
- documentation: 80% done
- coding: 30% done
- QA: 20% done
week 4: June 28 Mon - July 2 Fri
//(done) // Create ver 1 of documentation and send to tops for review