== Project Plan ==
 +
<s>Link to Project Plan: [[File:Microsoft Project - KPI PhaseII Project Plan v1.pdf]] --> Old</s>
 +
 +
 +
Link to Project Plan: KPI Phase 2, ASN ph 3, and DQ tasks: [[File:Microsoft Project - KPIPhaseIIASNPh3DQJan21.pdf]]
 +
 +
<s>
 +
 +
== 2012 ==
-
== 2012 Timeline Milestones Deadlines ==
 
=== May ===
=== May ===
* May 20:
* May 20:
Line 41: Line 49:
* 28 / Thur
* 28 / Thur
** 3662 (Dates KPI): 2nd release to QA/SIT;  
** 3662 (Dates KPI): 2nd release to QA/SIT;  
-
** '''Release to UAT1'''
+
** <strike> '''(3595 Cost KPI): Release to UAT1''' </strike>
-
** <strike>'''(3595 Cost KPI) : Release to Prod''' 6:30-7:30 pm EST</strike>
+
** <strike>'''(3595 Cost KPI): Release to Prod''' 6:30-7:30 pm EST</strike>
* '''29 / Fri'''
* '''29 / Fri'''
Line 48: Line 56:
* '''30 / Sat'''
* '''30 / Sat'''
-
** '''(3595 Cost KPI): Release to Prod''' 6:30-7:30 pm EST
+
** '''(3595 Cost KPI): Release to Prod''' 6:30-7:30 pm EST (subject to change due urgent GMS work)
=== July ===
=== July ===
Line 62: Line 70:
** '''3662 (Dates KPI): Release to UAT2'''
** '''3662 (Dates KPI): Release to UAT2'''
-
* '''11 / Wed'''
+
* '''7/ Sat'''
-
** '''3662 (Dates KPI): Release to Prod'''
+
** '''3695 (Cost per Unit KPI): Release to Prod'''
 +
 
 +
* 10/ Tu
 +
** transfer proj to Tira
 +
 
 +
* 12/ Th
 +
** Deploy to Dev for Tira to review and for QA to test - Tira found bugs and assigned them back
 +
** 3662: [DR/KPI] SOW 0 DR4: Dates KPI
 +
** 3668: [DR/KPI] SOW 1 (DR3) Spec gaps and some changes
 +
 
 +
=== Aug ===
 +
 
 +
* 18 / Sat
 +
:* '''Rel to Prod:'''
 +
:** 0003662: [DR/KPI] SOW 0 DR4: Dates KPI
 +
:** 0003668: [DR/KPI] SOW 1 (DR3) Spec gaps and some changes
 +
 
 +
=== Sep ===
 +
 
 +
* 15 / Sat
 +
** '''Rel to Prod:'''
 +
 
 +
</s>
 +
 
 +
=== 2013 ===
 +
==== Jan - Feb====
 +
* ASN phase 3
 +
:* To complete all Requirements:
 +
:* To complete Dev:
 +
:* To complete QA/SIT/UAT:
 +
:* Staging:
 +
:* Production:
 +
 
 +
* KPI phase 2
 +
:* To complete Dev: TBD - no later than 2nd week of Feb
 +
:* To complete QA/SIT/UAT: TBD
 +
:* Staging: TBD
 +
:* Production: TBD
 +
 
 +
* KPI phase 3
 +
:* To complete requirements: Feb 7
 +
:* To complete Dev: TBD
 +
:* To complete QA/SIT/UAT: TBD
 +
:* Staging: TBD
 +
:* Production: TBD
 +
 
 +
* DQ
 +
:* To complete Dev: TBD
 +
:* QA/SIT/UAT: TBD
 +
:* Staging: TBD
 +
 
 +
* Emergency Release
 +
:* Scheduled: Feb 22, 2013

Current revision as of 19:27, 31 January 2013


Contents

[edit] Project Plan

Link to Project Plan: File:Microsoft Project - KPI PhaseII Project Plan v1.pdf --> Old


Link to Project Plan: KPI Phase 2, ASN ph 3, and DQ tasks: File:Microsoft Project - KPIPhaseIIASNPh3DQJan21.pdf

[edit] 2012

[edit] May

  • May 20:
    • project STARTED
  • May 28, Mon, 9am EST:
    • 3567 DR1 : dev/QA completed and moved to SIT
  • May 29, Tue, 11 am EST:
    • 3567 DR1 : SIT completed and moved to UAT (demo to Marc)
    • 3575 Evaluate LogiXML: Report with time estimates presented to Marc

[edit] June

  • 1 / Fri
    • 9am EST: 3583 (DR2 part A): dev/QA completed and moved to SIT
  • 18 / Mon
    • 4pm EST: 3595 (Cost KPI) Marc demo to Simon
    • 5pm EST: 3662 (Date KPI): prelim design due to Marc
  • 20 / Wed
    • 3595 (Cost KPI): Dev completed, push to QA
    • 3662 (Dates KPI): spec completed, accepted by dev
  • 21 / Th
    • 3595 (Cost KPI): QA/bugfix/SIT completed
    • Staging created at the end of the day
  • 22 / Fri
    • 3662 (Dates KPI): dev started
  • 25 / Mon
    • 3662 (Dates KPI): 1st release to QA
  • 26 / Tue
    • 3662 (Dates KPI): 1st release to SIT
  • 28 / Thur
    • 3662 (Dates KPI): 2nd release to QA/SIT;
    • (3595 Cost KPI): Release to UAT1
    • (3595 Cost KPI): Release to Prod 6:30-7:30 pm EST
  • 29 / Fri
    • 3662 (Dates KPI): Release to UAT1
  • 30 / Sat
    • (3595 Cost KPI): Release to Prod 6:30-7:30 pm EST (subject to change due urgent GMS work)

[edit] July

  • 2 / Mon
    • 3662 (Dates KPI): 3rd release to QA/SIT
  • 5 / Th
    • 3662 (Dates KPI): 4th release to QA/SIT
    • 3662 (Dates KPI): dev/bugfix completed
  • 6 / Fri
    • Staging started (morning kiev time)
    • 3662 (Dates KPI): Release to UAT2
  • 7/ Sat
    • 3695 (Cost per Unit KPI): Release to Prod
  • 10/ Tu
    • transfer proj to Tira
  • 12/ Th
    • Deploy to Dev for Tira to review and for QA to test - Tira found bugs and assigned them back
    • 3662: [DR/KPI] SOW 0 DR4: Dates KPI
    • 3668: [DR/KPI] SOW 1 (DR3) Spec gaps and some changes

[edit] Aug

  • 18 / Sat
  • Rel to Prod:
    • 0003662: [DR/KPI] SOW 0 DR4: Dates KPI
    • 0003668: [DR/KPI] SOW 1 (DR3) Spec gaps and some changes

[edit] Sep

  • 15 / Sat
    • Rel to Prod:

[edit] 2013

[edit] Jan - Feb

  • ASN phase 3
  • To complete all Requirements:
  • To complete Dev:
  • To complete QA/SIT/UAT:
  • Staging:
  • Production:
  • KPI phase 2
  • To complete Dev: TBD - no later than 2nd week of Feb
  • To complete QA/SIT/UAT: TBD
  • Staging: TBD
  • Production: TBD
  • KPI phase 3
  • To complete requirements: Feb 7
  • To complete Dev: TBD
  • To complete QA/SIT/UAT: TBD
  • Staging: TBD
  • Production: TBD
  • DQ
  • To complete Dev: TBD
  • QA/SIT/UAT: TBD
  • Staging: TBD
  • Emergency Release
  • Scheduled: Feb 22, 2013