2011 Jan Sprint
From UG
(→Weekly updated Plan Jan 21) |
(→Weekly updated Plan Feb 4) |
||
(6 intermediate revisions not shown) | |||
Line 21: | Line 21: | ||
NOTE: Due date for .rmhR, it must be updated by the end of Thursday. | NOTE: Due date for .rmhR, it must be updated by the end of Thursday. | ||
Per Sasha and Kostya, ZK task and related tasks are requested to postpone to the next sprint because of the purchasing license. | Per Sasha and Kostya, ZK task and related tasks are requested to postpone to the next sprint because of the purchasing license. | ||
+ | Task 2721 has been created: purchase ZK lib | ||
Mantis: 2576, 2301, 2398, 2419, and 2507 | Mantis: 2576, 2301, 2398, 2419, and 2507 | ||
Line 28: | Line 29: | ||
=== Weekly updated Plan Jan 28 === | === Weekly updated Plan Jan 28 === | ||
NOTE: Due date for .rmhR, it must be updated by the end of Thursday. | NOTE: Due date for .rmhR, it must be updated by the end of Thursday. | ||
+ | |||
+ | ZK task and related tasks are requested to postpone to the next sprint because of the purchasing license. Task 2721 has been created: purchase ZK lib | ||
+ | |||
+ | Mantis: 2576, 2301, 2398, 2419, and 2507 | ||
+ | [[File:Jan27.jpg]] | ||
=== Weekly updated Plan Feb 4 === | === Weekly updated Plan Feb 4 === | ||
NOTE: Staging - Jan 31, Production - Feb 3 | NOTE: Staging - Jan 31, Production - Feb 3 | ||
+ | |||
+ | 2553 is released, but more requirement is needed, reuse the same mantis and move back to Dev-Est | ||
+ | |||
+ | 1892 was completed, but requested not to release, because BA needs to change the requirement | ||
+ | |||
+ | 2233 and 2619 are on going tasks; move to next sprint | ||
+ | |||
+ | 2419 and 2507 are related to 2576 and on going tasks; move to next sprint | ||
+ | |||
+ | 2673 was added on the sprint later on and was completed by Kostya | ||
+ | |||
+ | [[File:Feb4SprintPlan.JPG]] | ||
+ | |||
+ | === Production Release === | ||
+ | All tasks were completed and delivered on time! Except some of the exceptional tasks that need to move to the next sprint. | ||
+ | |||
+ | After the release (Friday Feb 4), we need to restart the tomcat on production server since there is some problem with generating pdfs doc, viewing, etc. |
Current revision as of 16:00, 4 February 2011
Contents |
[edit] Intro
Jan 2011 sprint plan:
- Staging Release: Jan31, 2011
- Production Release: Feb 3, 2011
[edit] Plan
NOTE: Please note that the task 2397 for Andriy was completed and be a part of Jan 6 released. It is still pending for Roma to test. Total hrs for this sprint with rmhR = 406
[edit] Weekly updated Plan Jan 14
NOTE: Due date for .rmhR, it must be updated by the end of Thursday.
[edit] Weekly updated Plan Jan 21
NOTE: Due date for .rmhR, it must be updated by the end of Thursday. Per Sasha and Kostya, ZK task and related tasks are requested to postpone to the next sprint because of the purchasing license. Task 2721 has been created: purchase ZK lib
Mantis: 2576, 2301, 2398, 2419, and 2507
[edit] Weekly updated Plan Jan 28
NOTE: Due date for .rmhR, it must be updated by the end of Thursday.
ZK task and related tasks are requested to postpone to the next sprint because of the purchasing license. Task 2721 has been created: purchase ZK lib
Mantis: 2576, 2301, 2398, 2419, and 2507
[edit] Weekly updated Plan Feb 4
NOTE: Staging - Jan 31, Production - Feb 3
2553 is released, but more requirement is needed, reuse the same mantis and move back to Dev-Est
1892 was completed, but requested not to release, because BA needs to change the requirement
2233 and 2619 are on going tasks; move to next sprint
2419 and 2507 are related to 2576 and on going tasks; move to next sprint
2673 was added on the sprint later on and was completed by Kostya
[edit] Production Release
All tasks were completed and delivered on time! Except some of the exceptional tasks that need to move to the next sprint.
After the release (Friday Feb 4), we need to restart the tomcat on production server since there is some problem with generating pdfs doc, viewing, etc.