== 2009 November 20-30 ==
== 2009 November 20-30 ==
-
=== '''Release has been postponed until Monday, Nov 30 ''' ===
+
=== '''Release to Staging has been postponed until Monday, Nov 30 ''' ===
''(Nov 24, Tue) from Alex''
''(Nov 24, Tue) from Alex''
* We postponed because we want to test/fix all other reports as much as possible, not just List CTs/In Transit
* We postponed because we want to test/fix all other reports as much as possible, not just List CTs/In Transit
Line 7: Line 7:
** p2) Main, Where Is, Daily
** p2) Main, Where Is, Daily
** p3) 6 internal reports
** p3) 6 internal reports
 +
 +
* I assume we can test Staging in one day and if no critical bugs found - we release into Production on Tuesday, Dec 1
=== Reminder: Thursday/Fri are holidays in the USA this week  ===
=== Reminder: Thursday/Fri are holidays in the USA this week  ===

Revision as of 17:38, 25 November 2009

Contents

2009 November 20-30

Release to Staging has been postponed until Monday, Nov 30

(Nov 24, Tue) from Alex

  • We postponed because we want to test/fix all other reports as much as possible, not just List CTs/In Transit
  • Priorities:
    • p1) In Transit / List CTs
    • p2) Main, Where Is, Daily
    • p3) 6 internal reports
  • I assume we can test Staging in one day and if no critical bugs found - we release into Production on Tuesday, Dec 1

Reminder: Thursday/Fri are holidays in the USA this week

(Nov 24, Tue) Alex

December Sprint - radically new approach

(Nov 24, Tue) from Alex This time we are dead serious about long term planning:

  • Sprints period will be 1 month not 1 week as before
  • Release will be always done once a month
  • All specs must be completed, estimated and pass QA
  • It will be very important not to over promise
  • Currently PM Team is reviewing all tasks with stakeholders and assigning urg/high/med/low priorities to each task. After that each task will be assigned tentatively one of the Sprints in Dec, Jan, Feb, Spring, Summer

Updates to Work-flow in Mantis: State field is out, etc

(Nov 23, Mon) from Alex

  • I