Dev News
From UG
(Difference between revisions)
(→Release has been postponed until Monday, Nov 30) |
(→Release has been postponed until Monday, Nov 30) |
||
Line 1: | Line 1: | ||
== 2009 November 20-30 == | == 2009 November 20-30 == | ||
- | === '''Release has been postponed until Monday, Nov 30 ''' === | + | === '''Release to Staging has been postponed until Monday, Nov 30 ''' === |
''(Nov 24, Tue) from Alex'' | ''(Nov 24, Tue) from Alex'' | ||
* We postponed because we want to test/fix all other reports as much as possible, not just List CTs/In Transit | * We postponed because we want to test/fix all other reports as much as possible, not just List CTs/In Transit | ||
Line 7: | Line 7: | ||
** p2) Main, Where Is, Daily | ** p2) Main, Where Is, Daily | ||
** p3) 6 internal reports | ** p3) 6 internal reports | ||
+ | |||
+ | * I assume we can test Staging in one day and if no critical bugs found - we release into Production on Tuesday, Dec 1 | ||
=== Reminder: Thursday/Fri are holidays in the USA this week === | === Reminder: Thursday/Fri are holidays in the USA this week === |
Revision as of 17:38, 25 November 2009
Contents |
2009 November 20-30
Release to Staging has been postponed until Monday, Nov 30
(Nov 24, Tue) from Alex
- We postponed because we want to test/fix all other reports as much as possible, not just List CTs/In Transit
- Priorities:
- p1) In Transit / List CTs
- p2) Main, Where Is, Daily
- p3) 6 internal reports
- I assume we can test Staging in one day and if no critical bugs found - we release into Production on Tuesday, Dec 1
Reminder: Thursday/Fri are holidays in the USA this week
(Nov 24, Tue) Alex
December Sprint - radically new approach
(Nov 24, Tue) from Alex This time we are dead serious about long term planning:
- Sprints period will be 1 month not 1 week as before
- Release will be always done once a month
- All specs must be completed, estimated and pass QA
- It will be very important not to over promise
- Currently PM Team is reviewing all tasks with stakeholders and assigning urg/high/med/low priorities to each task. After that each task will be assigned tentatively one of the Sprints in Dec, Jan, Feb, Spring, Summer
Updates to Work-flow in Mantis: State field is out, etc
(Nov 23, Mon) from Alex
- I