ASN 20 Timeline
From UG
(Difference between revisions)
(→Mon 8 to Sun 14) |
(→Sept) |
||
Line 47: | Line 47: | ||
* Mon | * Mon | ||
- | ** Final spec sign off meeting with Simon/Marc | + | ** <font color="red">Final spec sign off meeting with Simon/Marc</font> |
+ | ** Agreement with Kostya on Architecture / resource allocation / schedule | ||
+ | ** Agreement with Perry on resource allocation / schedule | ||
* Tue | * Tue | ||
+ | ** most mantis tasks created and assigned | ||
+ | ** schedule for next week finalized / disseminated | ||
+ | |||
* Wed | * Wed | ||
+ | |||
* Th | * Th | ||
+ | |||
* Fri | * Fri | ||
- | + | By the end of this week: | |
+ | * AG: SOW 7, 8 completed | ||
+ | * AK: SOW 2,3,4 completed; | ||
+ | * Kostya: | ||
+ | * Sasha: | ||
==== Mon 17 to Sun 23 ==== | ==== Mon 17 to Sun 23 ==== | ||
Line 64: | Line 75: | ||
* Fri | * Fri | ||
- | + | By the end of this week: | |
==== Mon 24 to Sun 30 ==== | ==== Mon 24 to Sun 30 ==== | ||
Line 74: | Line 85: | ||
* Fri | * Fri | ||
- | + | By the end of this week: | |
=== Oct === | === Oct === |
Revision as of 15:59, 11 September 2012
Contents |
2012
July
- July 1:
- project STARTED
- (scope/approach was reduced from ASN/I-Portal to fast track strictly ASN 2.0)
- Alex took over this project from Tira
- project STARTED
- July 1 - July 13 (2 weeks):
- Requirements Phase - completed
- July 16 - 20 (1 week):
- Elco visit + Alex's PTO
- July 23 - Aug 3 (2 weeks):
- Solution (Architecture/Design) Phase - completed
August
Week of Aug 6 to 10
- Mon, 6: Review of Solution (Marc/Alex), collecting feedback (significant changes requested)
- Mon-Fri: work on Final Version
Week of Aug 13 to 17
- Mon:
- Final version of Solution completed and disseminated
- Suggested WBS Work Breakdown Structure disseminated
- Tue:
- WBS approved
- Mantises created; developers assigned for estimation
- Fri:
- Tasks estimated
- Project Schedule / Release Date adjusted accordingly to estimates
Week of Aug 20 to 24
1st week of Construction/QA.
Sept
Mon 10 to Sun 16
- Mon
- Final spec sign off meeting with Simon/Marc
- Agreement with Kostya on Architecture / resource allocation / schedule
- Agreement with Perry on resource allocation / schedule
- Tue
- most mantis tasks created and assigned
- schedule for next week finalized / disseminated
- Wed
- Th
- Fri
By the end of this week:
- AG: SOW 7, 8 completed
- AK: SOW 2,3,4 completed;
- Kostya:
- Sasha:
Mon 17 to Sun 23
- Mon
- Tue
- Wed
- Th
- Fri
By the end of this week:
Mon 24 to Sun 30
- Mon
- Tue
- Wed
- Th
- Fri
By the end of this week:
Oct
- Mon
- Tue
- Wed
- Th
- Fri
- By the end of this week:
Mon 1 to Sun 7
- Mon
- Tue
- Wed
- Th
- Fri
- By the end of this week:
Mon 8 to Sun 14
- Mon
- Tue 16
- ASN 20 demo to EA
- Wed
- Th
- Fri
- By the end of this week:
L0 Schedule per Perry
Option 1 (crash - with new developers added and more aggressive schedules)
Construction 8/20/12 - 9/7/12 days=15 Sasha, AK Verif-n (UAT) 9/10/12 - 9/21/12 days=10 Sasha, Roma, AG, New Dev 2 (as QA) Buffer 9/24/12 - 10/5/12 days=10 Sasha, Roma, AG
Option 2 (baseline)
Construction 8/20/12 - 9/7/12 days=15 Sasha, AK Verification 9/10/12 - 9/28/12 days=15 Sasha, Roma, AG Buffer 10/1/12 - 10/19/12 days=15 Sasha, Roma, AG