ASN 20 Timeline

From UG

(Difference between revisions)
Jump to: navigation, search
(Week of Aug 13 to 17)
(Week of Aug 13 to 17)
Line 30: Line 30:
* Mon:  
* Mon:  
** Final version of Solution completed and disseminated
** Final version of Solution completed and disseminated
-
** Suggested Breakdown of Tasks disseminated
+
** Suggested WBS Work Breakdown Structure disseminated
* Tue:
* Tue:
-
** Breakdown of Tasks approved
+
** WBS approved
** Mantises created; developers assigned for estimation
** Mantises created; developers assigned for estimation
* Fri:
* Fri:

Revision as of 20:11, 9 August 2012


Contents

2012

July

  • July 1:
    • project STARTED
      • (scope/approach was reduced from ASN/I-Portal to fast track strictly ASN 2.0)
      • Alex took over this project from Tira
  • July 1 - July 13 (2 weeks):
    • Requirements Phase - completed
  • July 16 - 20 (1 week):
    • Elco visit + Alex's PTO
  • July 23 - Aug 3 (2 weeks):
    • Solution (Architecture/Design) Phase - completed

August

Week of Aug 6 to 10

  • Mon, 6: Review of Solution (Marc/Alex), collecting feedback (significant changes requested)
  • Mon-Fri: work on Final Version

Week of Aug 13 to 17

  • Mon:
    • Final version of Solution completed and disseminated
    • Suggested WBS Work Breakdown Structure disseminated
  • Tue:
    • WBS approved
    • Mantises created; developers assigned for estimation
  • Fri:
    • Tasks estimated
    • Project Schedule / Release Date adjusted accordingly to estimates

Week of Aug 20 to 24

1st week of Construction/QA.

L0 Schedule per Perry

Construction	8/20/12	- 9/7/12	   days=15
Verification	9/10/12	- 9/21/12	   days=10
Buffer         9/24/12	- 10/5/12	   days=10