UG:IP2 Timeline
From UG
(Difference between revisions)
(→About) |
(→Nov) |
||
Line 34: | Line 34: | ||
=== Nov === | === Nov === | ||
* TBD | * TBD | ||
- | ** Release to | + | ** '''Release to production''' |
+ | |||
=== Dec === | === Dec === |
Revision as of 21:15, 27 June 2012
Contents |
About
This wiki contains all important events associated with software development associated with a given project.
In bold are events that are of interest to the Product Team (Marc/Simon).
2012
July
- 13 / Fri
- Timeline will be converted from L0 (initial) to L1 (fine) estimates
- 26 / Th
- Shipper module: release to UAT
Aug
- 23 / Th
- Planner module: release to UAT
Sep
- 27 / Th
- Jaguar module: release to UAT
Oct
- 25 / Th
- Misc module: release to UAT
Nov
- TBD
- Release to production