UG:DR KPI Timeline
From UG
(Difference between revisions)
(→July) |
(→June) |
||
Line 23: | Line 23: | ||
* 20 / Wed | * 20 / Wed | ||
- | ** 3595 (Cost KPI | + | ** 3595 (Cost KPI): Dev completed, push to QA |
+ | ** 3662 (Dates KPI): spec completed, accepted by dev | ||
* 21 / Th | * 21 / Th | ||
- | ** 3595: QA/bugfix completed | + | ** 3595 (Cost KPI): QA/bugfix completed |
** Staging created at the end of the day | ** Staging created at the end of the day | ||
Line 33: | Line 34: | ||
* 25 / Mon | * 25 / Mon | ||
- | ** 3662: 1st release to QA/SIT | + | ** 3662 (Dates KPI): 1st release to QA/SIT |
* 27 / Wed | * 27 / Wed | ||
Line 39: | Line 40: | ||
* 28 / Thur | * 28 / Thur | ||
- | ** 3662: 2nd release to QA/SIT | + | ** 3662 (Dates KPI): 2nd release to QA/SIT; release to UAT1 |
=== July === | === July === |
Revision as of 16:54, 20 June 2012
Contents |
Timeline Milestones Deadlines
May
- May 20:
- project STARTED
- May 28, Mon, 9am EST:
- 3567 DR1 : dev/QA completed and moved to SIT
- May 29, Tue, 11 am EST:
- 3567 DR1 : SIT completed and moved to UAT (demo to Marc)
- 3575 Evaluate LogiXML: Report with time estimates presented to Marc
June
- June 1, Fri, 9am EST:
- 0003583 DR2 part A: dev/QA completed and moved to SIT
- 18 / Mon
- 4pm EST: demo to Simon
- 5pm EST: Date KPI prelim design due to Marc
- 20 / Wed
- 3595 (Cost KPI): Dev completed, push to QA
- 3662 (Dates KPI): spec completed, accepted by dev
- 21 / Th
- 3595 (Cost KPI): QA/bugfix completed
- Staging created at the end of the day
- 22 / Fri
- 3662 (Dates KPI): dev started
- 25 / Mon
- 3662 (Dates KPI): 1st release to QA/SIT
- 27 / Wed
- Release to Prod (3595 Cost KPI)
- 28 / Thur
- 3662 (Dates KPI): 2nd release to QA/SIT; release to UAT1
July
- 2 / Mon
- 3662: 3rd release to QA/SIT/UAT
- 5 / Th
- 3662: 4th release to QA/SIT/UAT
- 3662: dev/bugfix completed
- 6 / Fri
- Staging started (morning kiev time)
- 11 / Wed
- Release to Prod (3663 Dates KPI)