- | + | === May === | |
* May 20: | * May 20: | ||
** project STARTED | ** project STARTED | ||
Line 14: | Line 14: | ||
** 3575 Evaluate LogiXML: Report with time estimates presented to Marc | ** 3575 Evaluate LogiXML: Report with time estimates presented to Marc | ||
+ | === June === | ||
* June 1, Fri, 9am EST: | * June 1, Fri, 9am EST: | ||
** 0003583 DR2 part A: dev/QA completed and moved to SIT | ** 0003583 DR2 part A: dev/QA completed and moved to SIT | ||
Line 36: | Line 37: | ||
** release of Phase 1A.1 to prod | ** release of Phase 1A.1 to prod | ||
+ | === July === | ||
* July 6 Fri, 9,10,11 | * July 6 Fri, 9,10,11 | ||
** staging | ** staging |
Revision as of 16:12, 20 June 2012
Contents |
Timeline Milestones Deadlines
May
- May 20:
- project STARTED
- May 28, Mon, 9am EST:
- 3567 DR1 : dev/QA completed and moved to SIT
- May 29, Tue, 11 am EST:
- 3567 DR1 : SIT completed and moved to UAT (demo to Marc)
- 3575 Evaluate LogiXML: Report with time estimates presented to Marc
June
- June 1, Fri, 9am EST:
- 0003583 DR2 part A: dev/QA completed and moved to SIT
- June 18, 4 pm EST
- 4pm EST: demo to Simon
- 5pm EST: Date KPI prelim design due to Marc
- June 20
- 3595 Dev completed
- June 21 Thur
- QA/bugfix and rel to staging end of the day
- June 22
- 3662 Dates KPI started dev
- June 27 Wed
- Prod (3595)
- June 29
- release of Phase 1A.1 to prod
July
- July 6 Fri, 9,10,11
- staging
- July 11 Wed
- rel 3662 into prod