2012 March Apr Sprint
From UG
(Difference between revisions)
(→Info for 2012 Jan Feb Sprint) |
(→Info for 2012 Jan Feb Sprint) |
||
(2 intermediate revisions not shown) | |||
Line 2: | Line 2: | ||
- | == Info | + | == Info == |
- | '''Mantis''': | + | '''Mantis''': 15 |
*'''Start''': Mat 5, 2012 | *'''Start''': Mat 5, 2012 |
Current revision as of 21:04, 9 February 2012
[edit] Info
Mantis: 15
- Start: Mat 5, 2012
- Staging: Apr 6, 2012
- Production: Apr 12, 2012
Holidays in USA: 0
Holidays in Ukraine: 0
Significant PTO:
- Tira 2 weeks
- Denise 1 week
Development (non staging) days in Ukraine: 25
BA(non staging) days in US: 25
[edit] Dev hours
- Kostya
- days: 15
- ttl hours: 5h x 15 days = 75
- Sa, AK, Mi
- days: 25
- ttl hours: 7h x 25 days = 175
[edit] SA hours
- Al
- days: 25
- ttl hours: 5h x 25 days = 100
- Ti
- days: 25
- ttl hours: 7h x 25 days = 105