Revision as of 18:10, 12 December 2011
Info for 2011 Dec to Jan Sprint
Mantis: 0003297
- Start: Dec 12, 2011
- Staging: Jan 13, 2011
- Production: Jan 19, 2011
Holidays in USA: 2
- Monday, December 26 Christmas Day
- Monday, January 2 New Year's Day
Holidays in Ukraine: 3 (to be verified)
- 1st 2nd (Mon) and 3rd (Tue) January - New Year's Day and Festive Days Off
- 7th 8th 9th (Mon) January - Orthodox Christian Christmas Days
Significant vacations in Ukraine: 5
- dec 19-23 - all 4 developers will be on vacation (assume that Misha as well)
Development (non staging) days in Ukraine: 12
Dev hours:
- Kostya
- days: 17
- ttl hours: 5h x 17 days = 85
- Sa, AK
- days: 17
- ttl hours: 7h x 17 days = 119
- Mi
- days: 16
- ttl hours: 7h x 16 days = 112