Staging 19-Sep-11
 +
Production 22-Sep-11
 +
 +
Number of Days 19 --> Holiday Aug24 Ukrain independent day
== Plan to the Board ==
== Plan to the Board ==
-
=== Tira ===
+
See it by selecting "All projects" and S#="8d"
-
''Components:'' JagIT, Misc/Sys, help with other components.
+
=== Kostya ===
-
''Tasks:''
+
[[File:KostyaAug.JPG]]
 +
Please note that mantis 3117, Simon proposes a new requirement, please discuss with Alex. However the bug still need to fix. Up to you whether the new requirement can be done at the same time as the fixing bug or you would like to fix the bug first and work on the new requirement in the future. If the bug can be fixed with the new requirement, this task is not necessary to be included in this sprint.
-
* 0003116: (Client Watch List) Improving/expanding
+
=== Sasha ===
-
Requested by Simon! This needs spec!
+
[[File:SashaAug.JPG]]
-
=== Tracie  ===
+
=== Misha ===
 +
[[File:MishaAug.JPG]]
-
''Components:'' AccMisc, AccCore, AccReps, OpsPdfs, OpsReps (includes DRs/KPIs)
+
=== Andriy ===
 +
[[File:AndriyAug.JPG]]
-
''Tasks:''
+
=== Andrei ===
 +
[[File:AndreiAug.JPG]]
-
==== 0003129: [Rates DB] Implement phase 2 (CK model for Air Rates). Part B ====
+
=== Roma ===
-
 
+
[[File:RomaAug.JPG]]
-
==== (maybe start) 0003097: [Rates DB] Implement phase 3 (CK model for FCL) ====
+
-
 
+
-
=== from Denise ===
+
-
 
+
-
''Components:''  OpsCore, OpsMisc, Client
+
-
 
+
-
''Tasks:''
+

Current revision as of 15:48, 29 August 2011


Contents

[edit] Intro

Staging 19-Sep-11 Production 22-Sep-11

Number of Days 19 --> Holiday Aug24 Ukrain independent day

[edit] Plan to the Board

See it by selecting "All projects" and S#="8d"

[edit] Kostya

File:KostyaAug.JPG

Please note that mantis 3117, Simon proposes a new requirement, please discuss with Alex. However the bug still need to fix. Up to you whether the new requirement can be done at the same time as the fixing bug or you would like to fix the bug first and work on the new requirement in the future. If the bug can be fixed with the new requirement, this task is not necessary to be included in this sprint.

[edit] Sasha

File:SashaAug.JPG

[edit] Misha

File:MishaAug.JPG

[edit] Andriy

File:AndriyAug.JPG

[edit] Andrei

File:AndreiAug.JPG

[edit] Roma

File:RomaAug.JPG