2011 July August

From UG

(Difference between revisions)
Jump to: navigation, search
(Aug 15)
(Dev Sprint Manager and Support Manager role)
Line 235: Line 235:
''Currently in this role: Tira''
''Currently in this role: Tira''
-
Dev Sprint Management.
+
'''Dev Sprint Management:'''
* Before Sprint starts:
* Before Sprint starts:
Line 247: Line 247:
** email this project plan to everyone
** email this project plan to everyone
 +
* During the Sprint:
 +
** once a week look at tasks scheduled to be completed that week (in mantis sort by week# and see if there any tasks tagged for this week and still in Dev). If there are ask developer/BA why, what is the new estimate. Escalate issue to Dev Manager as required.
 +
** (optional but useful) have weekly status update meeting with all developers/QAs/BAs
 +
* At the end of the Sprint:
 +
**
==== Dev Manager and Technical Architect role ====
==== Dev Manager and Technical Architect role ====

Revision as of 16:11, 16 August 2011


Contents

Sprint Info

  • Start: May 30 Mon
  • Staging: July 4 Mon
  • Prod: July 7 Thu
  • Working Days: 23
  • Holidays: none

Daily Log

PM & Estim week schedule and project reviews with Sprint manager

  • Mon (Jul 4) - preliminary new Sprint plan is to be announced (Alex)
  • Tue - Smartphone App (Kostya)
  • Wed

- Int Portal (Sasha);

- EDI with Trenset (Misha)

  • Th - Rates DB (AK/Misha)
  • Fri - Dash/DashReps framework&reports (AK)
  • Mon & Tue (Jul 11, 12)

- follow up meetings for all key projects discussed last week - review of Dev Methodology, mantis structure, fields, roles and responsibilities, etc - New Sprint plan is to be confirmed

DT WUp - Dev team weekly updates meeting

  • When: Thursdays, 7-9 am
  • Who: all devs, QAs, Sup eng
  • Why:
    • individual updates from developers/QA/support:
      • explain tasks assigned
      • what work has been completed over last week
      • on schedule? behind schedule? why? how to improve? how to learn from this?
      • suggestions from everyone
    • updates/conclusions from Lead PM
      • old/new biz proc review\
      • systems review
      • updates from upper managers

Org chart

File:Orgchart2011april13.jpg

Roles and relationships

File:No SA process Apr 13.jpg

New Mantis

Folders

result

Name Descr
* Archived / Released All tasks that have been released, completed, discontinued, etc
* CT2 map All CT2 components, subcomponents, etc (a.k.a. “parents”)
* Watchlists / Files / Misc
0. Support Support related tasks
1. Backlog Dev backlog (pre-BA and tasks on hold)
2. BA Sprint tasks in current BA sprint
3. Dev Est tasks passed BA phase and in Estimation phase by development
4. Dev Sprint tasks in current Dev sprint
5. WU Backlog Wiki update backlog (tasks released but not wiki updated)

Fields

Name Meaning Type Possible Values
 %UAT to be discontinued?Numeric
 %WU to be discontinued?Numeric
.amh total num of dev man hours spentString
.emh estimated man hoursFloat
.emhR estimated man hours with RiskFloat
.rmhR remaining man hours (with Risk)Float
b? bug?Enumeration Y
comp CT2 componentEnumeration AccCore|AccMisc|AccReps|-|OpsCore|OpsMisc|OpsRep|OpsPdf|-|Misc/Sys|JagIT|-|Client|ClientReps|
p.BA Business AnalystEnumeration Denise|Tracie|Alex|Tira
p.Dev DeveloperEnumeration Kostya|Sasha|Koltsov|Mihail|Vlad|Andrei|Roma|Alex|Tira
p.MO Module OwnerEnumeration Simon|Marc|Karen|Alex|Chikei|All
p.SQA Systems and Quality AnalystEnumeration AG|Roma
phase Dev phaseEnumeration Dev|QA|UAT|WU
QApf passed QA?Enumeration pass|fail
Rel# Release number (discontinue?)Enumeration
Spec updated wiki spec updated after implementation?Enumeration Yes|N/A
Spr# Sprint numberEnumeration jan7-feb3|April|JA.dev|JA.ba|AS.dev|AS.ba
T PriorityEnumeration p0|p1|p2|p3|p4|p5|p6|p7|p8|p9

Aug 4

Todos Roma:

  • For Pdfs:
    • move all wikis from "Ops Pdfs Coommon" to "OpsPdfsMisc"; kill Common
    • move 1997 1686 1698 1755 1680 1666 into 664

For OpsReps:

  • move 1585 2036 into 1600

Todos AG:

  • create mantis and wiki struct for OpsCore, OpsMisc, Client and call(present) BA/SQA team for review

Todos Alex:

  • create mantis and wiki struct for JagIT, MiscSys and call(present) BA/SQA team for review

Aug 5 Fri

Roma todos:

  • when have time review all bugs in DevEst (count: 30). Suggest a list for next Spr.

Aug 6

Clients E0:

Cosmetech Mably Europe
Cosmetech Mably Int'l
Cosmetech Mably Int'l (HK) Ltd
Coty Australia
Coty Espana
COTY EUROPE
Coty Geneva S.A Div. CP Trex
COTY GERMANY
COTY ITALY
Coty Prestige Japan K.K.
Coty Prestige Southeast Asia (HK) Ltd
Coty Prestige Southeast Asia Pte. Ltd.
Coty Sanford
Coty Sanford Vendors
Coty Services and Logistics
Coty Shanghai
COTY SPAIN
Coty UK


Bill To:

COSMETECH MABLY EUROPE - GENNEVILLIERS
COSMETECH MABLY INTL (HK) LTD - CENTRAL
Coty US LLC - Sanford
COTY SERVICES AND LOGISTICS GMBH - MAINZ
COTY PRESTIGE SOUTHEAST ASIA (HK) LTD - Wanchai
COTY PRESTIGE SHANGHAI (HK) LTD - NT
COTY MANUFACTURING UK LTD - ASHFORD

Users:

10 users, all have email like @cotyinc.com

Aug 15

Columns for "View Issues" page in "3. Dev Sprint" folder:

Status ph s# T m MO BA QA Dv .e .eR .rR 1 2 3 4 b <checkbox> <edit pen> ID comp Summary

Aug 16

BA Sprint Manager and Solutions Architect role

Currently in this role: Alex

Dev Sprint Manager and Support Manager role

Currently in this role: Tira

Dev Sprint Management:

  • Before Sprint starts:
    • request wish list from BAs for next Spr
    • identify tasks that will roll over from current sprint
    • calculate emh per developer and make sure it is reasonable
    • if space permits add more tasks from "Dev Backlog"
    • send this list to BAs/MOs for review
    • schedule CT2 Board and confirm final version there
    • get together with BAs and map tasks into weeks (use 1,2,3,4 mantis fields to indicate num of week when task will be completed)
    • email this project plan to everyone
  • During the Sprint:
    • once a week look at tasks scheduled to be completed that week (in mantis sort by week# and see if there any tasks tagged for this week and still in Dev). If there are ask developer/BA why, what is the new estimate. Escalate issue to Dev Manager as required.
    • (optional but useful) have weekly status update meeting with all developers/QAs/BAs
  • At the end of the Sprint:

Dev Manager and Technical Architect role

Dev Sprint Manager and Support Manager role

Currently in this role: Kostya