(Feb 17 Weekly plan)
 
(6 intermediate revisions not shown)
Line 60: Line 60:
==== Feb 17 Weekly plan ====
==== Feb 17 Weekly plan ====
-
* Meeting with Marc for EA & CEI requirements (Marc was on site Feb 3, 2011) - First debrief completed
+
* Meeting with Marc for EA & CEI requirements (Marc was on site Feb 3, 2011) - First debrief '''completed'''
* Meeting with Marc, Alex, Karen, Tracie for Rate Database - Continue process once a week
* Meeting with Marc, Alex, Karen, Tracie for Rate Database - Continue process once a week
-
* Meeting with Alex, Denise, Tracie for TM Rate database - Completed discussed about Denise project' s issues
+
* Meeting with Alex, Denise, Tracie for TM Rate database - '''Completed''' discussed about Denise project' s issues
* Meeting with Alex, Tracie, Alexis, and Misha for Air Status and EU Adv Notice project - On going
* Meeting with Alex, Tracie, Alexis, and Misha for Air Status and EU Adv Notice project - On going
-
* Knowledge exchanges - Completed
+
* Knowledge exchanges - '''Completed'''
* Brainstorming requirements for rate database and TM rate database issue - On going
* Brainstorming requirements for rate database and TM rate database issue - On going
-
* Support TMS issue (Corrupted XML) - Friday 11 and Monday 14
+
* Support TMS issue (Corrupted XML) - Friday 11 and Monday 14 - '''completed'''
-
* IHEP (filled in) - Completed Friday 11 and Monday 14  
+
* IHEP (filled in) - '''Completed''' Friday 11 and Monday 14  
-
* SKU to Planner Import list and Web portal support - Completed
+
* SKU to Planner Import list and Web portal support - '''Completed'''
-
* Plans for Feb Dev Sprint plan (monitoring/updating/Analysis) - Completed updates
+
* Plans for Feb Dev Sprint plan (monitoring/updating/Analysis) - '''Completed''' updates
* Plans for Feb BA/SA Sprint plan:  
* Plans for Feb BA/SA Sprint plan:  
-
** 0002771: Add additional text content on dispatch confirmation email (Truck Dom - Web portal) - completed
+
** 0002771: Add additional text content on dispatch confirmation email (Truck Dom - Web portal) - '''completed'''
** AIR Status (Tracie)
** AIR Status (Tracie)
** EU Adv Notice (Tracie)
** EU Adv Notice (Tracie)
 +
 +
===== UAT/Wiki update =====
 +
[[File:Feb17.1.JPG]]
 +
 +
===== BA/SA Plan =====
 +
[[File:SAFeb.JPG]]
 +
[[File:BAFeb.JPG]]
 +
 +
==== Feb 24 Weekly plan ====
 +
* Meeting with Marc, Alex, Karen, Tracie for Rate Database - Continue process once a week
 +
* Meeting with Alex, Tracie, Alexis, and Misha for Air Status and EU Adv Notice project - On going
 +
* Plans for Feb Dev Sprint plan (monitoring/updating/Analysis) - Completed updates
 +
* Plans for Feb BA/SA Sprint plan:
 +
* Tasks have been added on this sprint
 +
* Continue working with Tracie for Air Status and EU Adv Notice
 +
 +
[[File:Feb24Tira.JPG]]
 +
 +
==== March 3 Weekly Plan ====
 +
* Meetings with Alex
 +
* Meetings with Tracie
 +
* Plans for Feb Dev Sprint plan (monitoring/updating/Analysis) - Completed updates
 +
* Plans for Feb BA/SA Sprint plan:
 +
* Tasks have been added on this sprint
 +
 +
[[File:March3.JPG]]

Current revision as of 21:02, 3 March 2011


Contents

[edit] About

[edit] Dec 2010

[edit] Dec 2010 Plan

Main Plan for EA enhancement: See attached spreadsheet from here here

Additional plan: see spreadsheet from here

File:DecTira.JPG

[edit] Jan 2011 Plan

Create 2 proposals to submit to EA for these 3 tasks below. Plan links to mantis 2687

File:TiraJan11.JPG


[edit] Jan 13 weekly update

File:Jan13UpdatedTira.JPG

[edit] Jan 20 weekly update

New tasks have been gradually added.

File:TiraJan20.JPG

[edit] Jan 27 weekly update

File:TiraJan28.jpg

[edit] Feb 3 weekly update

File:Feb3.JPG

[edit] Feb 2011 Plan

  • Meeting with Marc for EA & CEI requirements (Marc was on site Feb 3, 2011)
  • Meeting with Marc, Alex, Karen, Tracie for Rate Database
  • Meeting with Alex, Denise, Tracie for TM Rate database
  • Meeting with Alex, Tracie, Alexis, and Misha for Air Status and EU Adv Notice project
  • Knowledge exchanges
  • Brainstorming requirements for rate database and TM rate database issue
  • Support TMS issue (Corrupted XML)
  • IHEP (filled in)
  • SKU to Planner Import list and Web portal support
  • Plans for Feb Dev Sprint plan (monitoring/updating/Analysis)
  • Plans for Feb BA/SA Sprint plan:
    • 0002771: Add additional text content on dispatch confirmation email (Truck Dom - Web portal)
    • AIR Status (Tracie)
    • EU Adv Notice (Tracie)
[edit] =========================================================================================================================

[edit] UAT And Wiki update Plan

File:UATFeb.JPG

[edit] BA/SA Plan

File:SAFeb.JPG File:BAFeb.JPG

[edit] ========================================================================================================================

[edit] Feb 17 Weekly plan

  • Meeting with Marc for EA & CEI requirements (Marc was on site Feb 3, 2011) - First debrief completed
  • Meeting with Marc, Alex, Karen, Tracie for Rate Database - Continue process once a week
  • Meeting with Alex, Denise, Tracie for TM Rate database - Completed discussed about Denise project' s issues
  • Meeting with Alex, Tracie, Alexis, and Misha for Air Status and EU Adv Notice project - On going
  • Knowledge exchanges - Completed
  • Brainstorming requirements for rate database and TM rate database issue - On going
  • Support TMS issue (Corrupted XML) - Friday 11 and Monday 14 - completed
  • IHEP (filled in) - Completed Friday 11 and Monday 14
  • SKU to Planner Import list and Web portal support - Completed
  • Plans for Feb Dev Sprint plan (monitoring/updating/Analysis) - Completed updates
  • Plans for Feb BA/SA Sprint plan:
    • 0002771: Add additional text content on dispatch confirmation email (Truck Dom - Web portal) - completed
    • AIR Status (Tracie)
    • EU Adv Notice (Tracie)
[edit] UAT/Wiki update

File:Feb17.1.JPG

[edit] BA/SA Plan

File:SAFeb.JPG File:BAFeb.JPG

[edit] Feb 24 Weekly plan

  • Meeting with Marc, Alex, Karen, Tracie for Rate Database - Continue process once a week
  • Meeting with Alex, Tracie, Alexis, and Misha for Air Status and EU Adv Notice project - On going
  • Plans for Feb Dev Sprint plan (monitoring/updating/Analysis) - Completed updates
  • Plans for Feb BA/SA Sprint plan:
  • Tasks have been added on this sprint
  • Continue working with Tracie for Air Status and EU Adv Notice

File:Feb24Tira.JPG

[edit] March 3 Weekly Plan

  • Meetings with Alex
  • Meetings with Tracie
  • Plans for Feb Dev Sprint plan (monitoring/updating/Analysis) - Completed updates
  • Plans for Feb BA/SA Sprint plan:
  • Tasks have been added on this sprint

File:March3.JPG